It has been an exciting time in Hale County for the First Congregational Church Hall team! Here’s where we are right now: We’ve moved forward substantially, driven by our progress on the tongue-and-groove Timber Insulation Pod and insights from engineer Joe Burns and architects Cheryl Noel and Ravi Ricker of Wrap Architecture. We’ve designed the superstructure, adding a ridge beam, and confirmed our compliance with codes. Then we refined the design for the foundation and prepped the site. Now we’re marking out the foundation’s footings and preparing to break ground!
So, how did we get here? Let’s step back to Pig Roast in the spring. Our first “must do” was testing and constructing the structure of the tongue-and-groove Timber Insulation Pod, because the Pod represents how the Church Hall structure will eventually appear. Alongside this progress, we constructed a to-scale frame of the Church Hall’s north wall to represent the size and feel of the building, something visitors would see at a later stop on the Pig Roast tour. To top it all off, we drew new iterations of exterior perspectives, interior perspectives, and plans and sections of both the buildings and the site to really test the version of the design we presented at Pig Roast.
Finally, the day of the event arrived. We presented our First Congregational Church Hall work in the church itself thanks to help from, and coordination with, the congregation. After the presentation, everyone walked outside to view the string projection of the courtyard’s layout and the inclined walking path and to see how these combined with the building footprint. It was an incredible opportunity to present our latest work to so many new people.
Once the Pig Roast festivities concluded, we trekked back to Auburn, AL, for the Auburn University Spring 2026 Commencement (Graduation) ceremony. The four of us on the First Congregational Church Hall team, as well as those on the Deborah’s Home team, have officially graduated. Those B. Arch degrees didn’t earn themselves!
Returning from graduation, we hit the ground running on the construction of the Timber Insulation Pod. We finished building the floor, which included insulation and electrical wiring. Then the tongue and groove decking went up on the roof, walls, and floor. Right after that, we framed and sheathed the gable-end walls. After we had our walls and roof, it was time to install openings and begin insulating.
While work on the Pod continued throughout the summer and into the fall, so did the design progress on the Church Hall. Structural engineer Joe Burns helped us finalize the primary structure with the addition of a glue-laminated ridge beam. We always check that our designs comply with the International Building Code, but the extra eyes of professionals make us confident: We’re grateful to architects Cheryl Noel and Ravi Ricker of Wrap Architecture for verifying that we aren’t missing any major details. During the design of the superstructure, we kept pushing forward on drawings for the foundation. Now that the trees on-site have been cut down, we are currently marking out the foundation footings, and we’re preparing to break ground very soon!
That’s all for now from the First Congregational Church Hall. Up next will be further progress on the Timber Insulation Pods and updates on breaking ground for the Church Hall!
This semester, our 3rd-year class has balanced studio and site work, hands-on construction in woodshop, history class, and life in Newbern. From studying architectural details to working on Mark’s Home, we have continued to develop our skills while learning from one another and the surrounding community.
Studio: Many Hands, One Home
We began the semester by studying existing drawings of a chicken coop and redesigning details such as a folding door, nesting boxes, and the roof. Next, we assembled our revised designs, improving construction details through hands-on work. Our focus then shifted to Mark’s Home. Using existing construction documents, we created digital models to better understand the house and identify potential issues before continuing construction.
On-site, we work in four teams: Interiors, Surfaces, MEP, and Enclosures. In these teams, we created a schedule to map out the rest of the semester of work at Mark’s Home. Each group outlined its responsibilities and organized upcoming work into a timeline, filling an entire wall with the steps needed to move the project forward. This process gave us a shared view of the work ahead.
The MEP team ran the main water line to the water heater, installed the drain and vent systems, and began running water supply lines throughout the house. The Interiors team installed blocking for cabinets, vanities, built-ins, and closets. They also developed kitchen cabinet configurations and selected cabinetry for the kitchen, bathroom, and laundry room. Following a lighting workshop led by Thomas Paterson of Lux Populi and group design discussions, the Enclosures team designed and installed the cladding for the ceiling over the outdoor workshop space. The Surfaces team detailed the deck and ramp surfaces while developing a cladding system for the storm shelter.
Through this work, we continue to bring Mark’s Home from drawings to reality while gaining experience on the job site.
Picture day!Digital 20k reviewWorking through the detailsCleaning panels for the coopSanding away!Chicken Coop progress reportMeeting Mark!Color conference with MarkBlocking, blocking, blockingGetting the supply lines readyGetting supply lines ready pt.2Decisions decisionsWorkshop ceiling surface going upGetting ready for paint
History: A Sense of Place
Our History class takes us beyond the classroom to study historic buildings and document their architectural details. Throughout the semester, we have visited historic properties in Demopolis, Greensboro, and Tuscaloosa to examine construction methods and learn about each building’s history.
At the end of each class, we sketch the building we have just visited. These drawings help us record dimensions and architectural details. We sometimes add color using watercolors made from natural pigments gathered from materials around Newbern. We learned how to make our own watercolor pigments this way in a workshop led by local artist and maker Aaron Head.
By turning these materials into watercolors, we incorporate colors from the surrounding landscape into our sketches and create a visual record of the places we visit. This also helps us get some practice before we create our final watercolors for the semester.
Making charcoal at Sumac CottageIndigo dye workshopIndigo creativity!Creating our own watercolors from natural materialsExploring historic barnsGetting the inside scoop from Instructor Dick HudgensHistory adventures“Hey MTV, Welcome to my crib”Getting some sketching practice in along the way
Woodshop: Measure Twice, Cut Once
In the Woodshop, our goal for the semester is to recreate four chairs designed by famous architects. We began by creating storyboards of our selected architectural chairs, researching their designs, documenting dimensions, and studying their individual components. From there, we began building mock-ups to test proportions, connections, and assembly methods while also making cutting boards to practice woodworking techniques and become familiar with the woodshop’s tools and equipment. Working through both projects has helped us develop our skills and prepare for the final construction of our chairs.
Prepping cutting boardsStarting our chairs!CLAMP!
Student Life: Making Ourselves at Home
Outside our classes, we make time to spend together and explore Newbern. Each morning, a rotating group of 3rd-year students leads a 15-minute drawing exercise, with a different subject chosen each day. After Auburn’s last-second win against Georgia, we rolled a large tree outside to celebrate, carrying on the university’s tradition of rolling the trees at Toomer’s Corner—except here, instead—after a big victory. Every Sunday, a group of 3rd-Years organizes a cookout, dividing up supplies and preparing a meal together. We also gather around campfires to roast hot dogs and make s’mores after a long day’s work. We have also explored the surrounding landscape, including hiking to the rocky beach along the river at Perry Lakes Park, swimming in the rivers, and generally enjoying the outdoors.
These shared experiences have become an important part of our time at Rural Studio, giving us opportunities to connect outside of work and to make Newbern feel like home.
Howdy!Sketching clubCatching candy at the Homecoming paradeFarm fresh baby!Game nightWAR EAGLE!
Check back in to keep up with our progress this semester!
Summer to Fall building the timber Dining House and learning about the importance of tolerance in wood construction!
Once the spring semester was finished and subsequently our foundation was done, we felt a brief sense of relief. Months of building up confidence in construction skills and knowledge about our design, especially through the mock-up, left us in an optimistic place to tackle the one of most consequential phases of the project: The Timber Structure.
Our goal has always been to use materials that we have, heavily featuring our milled lumber and rough sawn lumber to match. Accordingly, we really had a lot to learn, and we are still learning about all of the lumber’s quirks. Using these materials meant doing lots of preparation before installing large ticket items like ridge beams, columns, and rafters. So here’s an effort to walk you through where we have been, the whole process, both gratifying and exhausting!
Look at those clean 90-degree angles!Mud-sill in and ready to go
The first step in the sequence was setting up two cleanly framed boxes on the north and south of the building to act as a base for the spine of the building to rest on. The beginning of the process had familiar components, like termite shields, mud-sills with drive pin nails, and initial 2×6 walls with studs 24″ O.C. (on center). Our mock-up made us think twice about craftsmanship, so we really took the time to clamp pieces, brace in multiple directions, and always check the level.
Our first walls go up!Building stud columns“Hey, check the level!”Transcribing studs on to base + top plates
Within normal stud walls, we had to account for the north/south flanking walls being both shear walls but also walls with embedded columns plus window and door openings. We set up the supports for the columns, pulling strings to make sure that each lined up within a ½” tolerance to one another. Sheathing afterwards was simple because we had a nice set of framed walls to work with. We were careful to stop at certain points and keep edges clean to create a good base for finishing the walls down the road. Seeing our framed boxes was exhilarating because we were able to start visualizing the space.
123Yay!
Even though the next step sounded easy—installing the mass timber—it was not simple! Each element of the ridge beam, columns, and rafters included subsequent preparation. In this process, we moved these heavy pieces of wood out of the barn with many hands. Next, we cleaned and treated the timbers with two different types of sprays, both equally important in deterring mold and pests while also providing future protection from water.
Spraying wood borate + wood forceStaying organized with pieces
Each element had a separate cut sheet (list of specifications) for sizing, which always cross-referenced the site conditions. Then the preparation came down to cutting, notching, chiseling, screwing together, and finally drilling holes. We were always careful to check and re-measure with every move!
The widow maker…Stainless steel screws at 12″ O.C.Big clamps!Ridge beam prepClamping, measuring, and screwing raftersOur columns in all their glory! Ready to be notched accordingly
Installation was phased. We started with the defining moment of installing the ridge beam. We dropped in the three different pieces methodically, finishing with the middle piece, which is held with four threaded rods at both connections. Because we used an 18″-diameter pine log for the wood of our ridge beam, we couldn’t anticipate all of the nuanced details of the install and finished look. We approached the task with this in mind, and we successfully installed the beam, stabilizing it with 3′-long metal straps, with roughly 40 nails in each!
41 nails and 3′ feet of steel later…The Dining House after rafter 01
After the ridge beam, we focused on gathering site measurements to predict where the rafters would sit and cut notches. Detailed work created a slow pace, but a pace that was necessary to install rafters and columns correctly. We started with a “mock-up” of the installation, placed the next two rafters as anchors over the attic, and placed the last three—perhaps the most important ones—visually connecting to the east and west walls. Correct alignment was essential for both the aesthetics and to have the right load paths. Part of the structure serves as a built-in seat on our east- and west-flanking walls. The alignment right was crucial, not only for the seat to be visually pleasing but also for so we could install the glass properly and complete the final finishes. The process was a lot of work!
Craning one side after the otherMaking sure the connection slots into placeAlways check the level!Drilling holes for threaded rodsBelaying a rafter!
After all of that, lots remained to do (and we still have lots to do, of course)! We had to place tie downs on stud walls, as well as install threaded rods at joints in the mass timber and bracing at every critical point. The goal for us is to always level and brace better than we installed it.
Installing and tightening threaded rod connectionsClamps: Friend or Enemy?
We learned important lessons about the strength and unpredictable nature of wood, which surprised us during the hot and humid moments this season. With every step we make, we anticipate the challenges a little more and learn how to work against the grain! Stay tuned because it is just getting interesting!
We have been busy worker bees at Smith Park over the past few months, zipping back and forth across the site and checking tasks off our to-do list. With the end of construction in sight, each completed concrete pour, edging piece, and gravel courtyard feels like a huge achievement!
Chain Link Set Up around the Site
In August’s “Neckdown”—when everyone pitches in on physical tasks—a throng of new students came to the park to help us trim, hang, and secure all the chain-link screens. We salvaged almost all the materials from the old baseball fencing that was taken down at the beginning of 2025. The collection of 36 bays holds screens that vary in height and angle, resulting in a dynamic, sculptural screen that defines the basketball and field spaces.
salvaged chain link poles, image from Jan 2025rolls of chain link on court were salvaged from old field
Groundwork
Many tasks at the park recur, especially pouring concrete. Each pour has a big impact: finishing out the south loop, tying into the bathroom slab, and edging the gravel courtyards. We have completed 18 pours so far, which makes what I’m about to say very exciting: We have only ONE MORE concrete pour to go to complete the trail!
Images below show the formwork and excavation process for the concrete benches at the entrance to the park.
The mound is turning green! It received its final shaping in the spring, and we seeded grass right after. To keep the seed from being washed away, we applied a layer of hay like a blanket. Now the green grass is overspreading the mound—a much nicer color than that crunchy beige hay!
grass beginning to grow on field and moundthe most recently pour trail leading to the grassy mound
Edging and Gravel work
Lights… speakers… we are ready for a party at Smith Park! The community space now has electricity tied in, and we’ve completed the finishing touches on the gravel. The pavilion is ready to host any birthday party or community grill out.
When we aren’t pouring concrete, we’re shoveling a variety of dirt and gravel. The hard work is paying off: The courtyard spaces at the entrance are also receiving their final layers of gravel.
Trees and Shrubs—Working Through the Details
The cool fall weather means that the planting season for trees and shrubs has finally returned. While the weather was still warm, we began preparing the soil for shrubs and working through the planting process. We removed soil from spots that were compacted and full of asphalt (the legacy from an old parking lot) and supplemented those areas with topsoil. After a few days in the skid-steer loader, the soil is ready for shrubs and mulch, both coming soon!
The Sign, Properly Placed
From expensive fabrication drawings to installation, the sign has been a labor of love. Although the Smith Park sign shares cosmetic features with the Lions Park gate, the mechanism for erecting and securing it is completely different. Each segment of the sign is tied down into two 4-ft-deep footings: nice and sturdy! The sign will soon sport a bright and shiny new layer of paint, so keep an eye out for this fabulous makeover.
E8CDC Builds on Small Lots in Hilly Eastern Tennessee
Eastern Eight Community Development Corporation (E8CDC) is expanding housing opportunities in their corner of Northeast Tennessee and has been a valued long-term partner of the Front Porch Initiative (FPI). After finishing a home together in 2022, we’re celebrating another recently completed infill house—a new house on a vacant or underused lot in a existing neighborhood—this time just one mile from downtown Bristol, TN!
Meeting the Challenge
In April of 2023, E8CDC acquired a small, steeply sloped parcel in Bristol, TN, a lot condition that is common in this corner of Tennessee. E8CDC received U.S. Housing and Urban Development (HUD) funds through the Northeast Tennessee/Virginia HOME Consortium to conduct the environmental review, demolish the existing neglected house, and site survey.
The lot is considered nonconforming because it doesn’t meet minimum lot area required by Bristol Zoning Code. In addition, the site’s layout requires a zoning variance to meet the required side setbacks. However, even with the variance, the buildable area of the site was only 35 feet by 42 feet.
The small buildable footprint and significant slope in grade were major factors in planning the house. The Front Porch Initiative modified Auburn University Rural Studio (AURS) Patriece’s prototype from a two-story house into a one-story, two bedroom, one bathroom home. This variation has a zero-step accessible entry into the main floor at street level and a walk-out basement below. The basement helps manage the steep slope, while providing space for the water heater and mechanical systems, keeping them inside the thermal envelope of the building and thereby lengthening the equipment’s lifespans.
Strategic Building
Once the original home was demolished and the disturbed soil removed, E8CDC and FPI rotated the home so that the long side would be parallel to the road. That orientation allows the basement foundation walls to be designed to act as retaining walls for a parking pad on the high side of the site. A key takeaway from this project was how to use existing site features to our advantage, retaining earth and enhancing site access.
In October 2025, E8CDC hired a general contractor to work alongside their new construction manager to oversee the project on-site. They opted for a poured-in-place concrete wall instead of a CMU block wall, allowing them to quickly complete a stronger and water-tight foundation, which was ready by mid-October. By the end of the month, the team had finished the floor system, framed the walls, erected roof trusses, and applied exterior sheathing, significantly speeding up the construction schedule to meet their grant deadlines.
Home Performance
Throughout construction, a Home Energy Rating System (HERS) rater assessed this home. E8CDC was familiar with the HERS rater, who evaluated the East Unaka home completed in 2021. The assessment included a mid-construction blower door test, which examines how airtight the home is, calculating the home’s air infiltration rate in air changes per hour (ACH). The lower the ACH, the tighter the thermal envelope and the better the home’s energy efficiency. The goal is always to mitigate air infiltration, and a mid-construction check allows for improvement. We were pleased that the final blower door test results were low 2.1 ACH (air changes per hour), a low score for a home (code requires 5 ACH)! Finally, the rater evaluated the finished house, rating it with a HERS Index. Because this home was built with such a tight envelope, the homeowner minimizes air leakage which reduces stress on the air conditioning systems, saving money and staying comfortable.
Balancing Affordability Opportunities
The HUD grant that funded this home has caps on buyer income and rental reimbursement. For a two-bedroom home, the maximum homebuyer income is limited to 80% AMI (area median income), and the maximum rental reimbursement is $1,100/month. These requirements influenced E8CDC’s decision to keep the home as rental housing, to better recover the cost of its construction.
Rural Studio is proud the home is finally complete! Even though there were challenges, we are honored to collaborate with housing partners that are persistent and dedicated to providing housing affordability in their community!
Watauga Street
Gentle Density
While Lilly St began development, E8CDC also reached out to Rural studio about another site about 40 minutes away in Johnson City, TN. Based on the city official’s desire to increase residential density, Eastern 8 was originally considering building a quadplex on a site. But eventually, they decided that subdividing would be more appropriate for the neighborhood: they divided the lot in half and developed two separate duplexes.
An Adaptable Prototype That Meets Local Needs
Auburn University Rural Studio had previously designed a duplex that was built for the New Orleans area Habitat for Humanity to hold as workforce housing. Because E8CDC wanted to use a duplex for rental property, AURS was able to advance this previous design into a prototype that can be flexible to multiple housing needs: AURS created interchangeable options of bathroom and storage spaces. The adaptability of the duplex prototype allowed E8CDC to market the project to a specific housing need. E8CDC selected the option with one bathroom and a laundry room then requested that the units be fully accessible, as they intend the units to be rentals for veterans and want to support residents throughout different stages of life.
The two duplexes, instead of one quadplex, fit into the urban fabric of the single-family home neighborhood, and creates new opportunities for shared outdoor space and resources. The design encourages neighborly interaction: residents share off-street parking at the front of the site, share access to the duplexes through an interior courtyard with interior-facing porches.
Energy Efficient Improvements
Recognizing that the units will be made available to residents who may be on fixed incomes, E8CDC agreed to pursue ENERGY STAR certification to reduce energy costs, thereby ensuring long-term affordability to residents. Energy modeling estimates that, because of efficient design, the home will consume 46% less energy than a typical US home. The energy improvements include improved air sealing, balanced ventilation, high-performance heating and cooling systems, and beyond-code insulation levels.
Construction of the duplexes began in October of 2025, and they were completed in July of 2026, with renters already approved to move into three of the four units. The project follows HUD income-based affordability guidelines, serving residents earning 80% AMI or below for rental monthly rates.
E8CDC hosted a ribbon cutting ceremony in July. The Federation of Appalachian Housing Enterprises (FAHE) provided some of the grant funding for this project, were in attendance to celebrate the project opening. The Front Porch Initiative, members of the E8CDC board, and local community members all gathered to celebrate this successful effort to provide east Tennessee with housing that is affordable to those who live there!