It might still be raining, but the rain delay is over for the 3rd-years! It’s about time here at 20K Ophelia’s Home, but the framing of the floor above the crawlspace foundation is finally complete. As the rainy days are starting to become less frequent, there has been more time for the 3rd-years to progress forward with construction.

Enclosures team finished up the last details on the termite flashing, figuring out a neat corner solution along with the flashing dipping down to cover where the girders rest.

Wednesday was a charrette day back in studio, and the walls have never been more colorful! Ideas upon ideas were put on paper as the whole day was spent exploring options for the porch on Ophelia’s Home. The 3rd-years will continue to refine the design for Ophelia and the site.

There were a few road bumps while building the flooring because we discovered the foundation was not completely square and is now a ~soft~ trapezoid. Having to work around a funky foundation, the framing team became pros at leveling and squaring the floor framing. In order to make sure the floor was entirely level, they carefully worked to correct the rim joists by pushing them towards the crawlspace in some spots. Once the shimming and squaring was done and checked (and checked again, and maybe redone in a few places, then checked some more) it was smooth sailing to place in the rest of the joists and blocking.

To cap off a busy week , sub floors were put into place on the joists. The floors might be blue, but the 3rd-years sure weren’t as they finished up with a layer of waterproof paint that matched the much anticipated clear sky above.