From a pile to a truckload!

After months of fabricating at the shop, we are finally back in Hale! Thanks to Mason, and Shane from Stillwater, we were able to take all the pieces from Jim’s shop to Metal Works, and finally to Morrisette.

The last few pieces the team worked on were for the walkway, which were dry-fitted at the shop before delivering everything to the galvanizing plant.

We are incredibly grateful for the opportunity to have spent time at the shop and become empowered with new metalworking, and welding skills!

Luis at the grill

What is a celebration without tacos? After wrapping up fabrication, Luis and Flo made carne asada and al pastor tacos! A huge shoutout for them, not only for teaching us, and making sure we didn’t injure ourselves but for sharing stories and becoming part of our team.

Week 76

Hi friends! Lots to catch up since our last post! After many weeks of rain in April, we have designed, built, put up and down our full-scale mockup. Some on Morrisette to test if the 18’ screens would stand safely, and finally on site. As always mock-ups are the best tool for making decisions, so as we were putting up the screens, we made some changes to the design as we saw how the space shaped out. Also, thank you Andrew, Steve and Mass Timber team for helping us raise the 18′x18′ Screens!

Luckily the mock-up was ready by the time Pig Roast came around the corner, and it helped us study how people inhabited the space. Not only as a large crowd but also when the Horseshoe Farm Fellows had one of their weekly meetings in the courtyard.

We have also had many pin ups and meetings in the last 2 months. We had a chance to meet with Zane Morgan and Cassandra Kellogg twice! They are not only super generous with their time, but also incredibly helpful when talking to us through some of the details we have been working through. We also had a visit from David Hinson, whose excitement about the project energized us to keep pushing forward! As well as a long, but incredibly helpful call with David Hill, in which we learned some more key information about tree choosing, and soil conditions of our site.

Additionally, in the last two weeks, we have spoken to Joe many times, in order to work through some of the structural questions of the walkway and screens. We also visited Jim Turnipseed to update him on the newest design proposal. We are incredibly thankful for Jim’s generosity with material donations and for letting us use his shop when the time comes to fabricate the screens!

Week 69

East facing elevation shows 18′ screens that slip past balcony datum line to separate the two elements. We are also working through options for the “porch” on the Southern portion of the site, we are interested in using lights or a dropped ceiling to lower the scale.

We finally modeled our most recent design! This past week we shifted from plans, sections and SketchUp to a physical model, so we could charette through the tree and furniture placement.

Stepping out of the waiting room looking towards the active space and porch.

Part of figuring out the tree layout is understanding how it shapes the north end, as another entrance to the courtyard as well as what it gives back to the street since it is the most public area of the design. 

Stay tuned as we work through the different options for the railing (not featured in model at the moment) and its interaction with the screens!