trees

Busy Bees at Smith Park

We have been busy worker bees at Smith Park over the past few months, zipping back and forth across the site and checking tasks off our to-do list. With the end of construction in sight, each completed concrete pour, edging piece, and gravel courtyard feels like a huge achievement!

Chain Link Set Up around the Site  

In August’s “Neckdown”—when everyone pitches in on physical tasks—a throng of new students came to the park to help us trim, hang, and secure all the chain-link screens. We salvaged almost all the materials from the old baseball fencing that was taken down at the beginning of 2025. The collection of 36 bays holds screens that vary in height and angle, resulting in a dynamic, sculptural screen that defines the basketball and field spaces.

Groundwork

Many tasks at the park recur, especially pouring concrete. Each pour has a big impact: finishing out the south loop, tying into the bathroom slab, and edging the gravel courtyards. We have completed 18 pours so far, which makes what I’m about to say very exciting: We have only ONE MORE concrete pour to go to complete the trail!

Images below show the formwork and excavation process for the concrete benches at the entrance to the park.

The mound is turning green! It received its final shaping in the spring, and we seeded grass right after. To keep the seed from being washed away, we applied a layer of hay like a blanket. Now the green grass is overspreading the mound—a much nicer color than that crunchy beige hay!

Edging and Gravel work

Lights… speakers… we are ready for a party at Smith Park! The community space now has electricity tied in, and we’ve completed the finishing touches on the gravel. The pavilion is ready to host any birthday party or community grill out.

When we aren’t pouring concrete, we’re shoveling a variety of dirt and gravel. The hard work is paying off: The courtyard spaces at the entrance are also receiving their final layers of gravel.

Trees and Shrubs—Working Through the Details

The cool fall weather means that the planting season for trees and shrubs has finally returned. While the weather was still warm, we began preparing the soil for shrubs and working through the planting process. We removed soil from spots that were compacted and full of asphalt (the legacy from an old parking lot) and supplemented those areas with topsoil. After a few days in the skid-steer loader, the soil is ready for shrubs and mulch, both coming soon!

The Sign, Properly Placed

From expensive fabrication drawings to installation, the sign has been a labor of love. Although the Smith Park sign shares cosmetic features with the Lions Park gate, the mechanism for erecting and securing it is completely different. Each segment of the sign is tied down into two 4-ft-deep footings: nice and sturdy! The sign will soon sport a bright and shiny new layer of paint, so keep an eye out for this fabulous makeover.

Tree Talk—The Smith Park team is developing green thumbs

An update on the basketball court, planting trees during neckdown, and pouring the first section of the walking trail.

Where we left off

Last year we prepped for the holidays by installing the basketball court at the park. You can read about how we prepared the formwork and installed the hoop posts in our last blog. Since then, we’ve applied a burlap finish to the court and cut all the control joints. A design is also in the works for a graphic painting on the court surface—something playful, colorful!

An overview of the order of—PEMDAS

Our project site is 2.5 acres, and we are touching almost every foot of it. That is a lot more square footage than a house! A big design challenge for us in recent days has been the staging and sequencing of construction. We are balancing tree delivery and installation, concrete pours, and more. To walk our readers through the order of events, we can apply a familiar algebra anagram PEMDAS.

Planting trees

The winter months are planting season, and we are looking to plant 115 trees at the park! Our goal is to get them in the ground before the weather gets too hot, so planting is our first priority. The first batch to be planted included seven black gum trees and three willow oaks. Lots of people helped during “Neckdown” Week , our time to maintain properties and make big project pushes. These helpers included our friends in Auburn University’s Landscape Architecture Program, all with their aid, 10 trees were installed in a little over a day!

Excavating the trail: Part 1

After we planted the trees, our friends at C&T Excavating came back and helped us with the excavation and base work for the first section of walking trail. Excavation for the trail is being divided into three parts. This strategy maintains truck access for concrete and tree deliveries while keeping the working area at a more manageable scale.

Make formwork

This part was pretty straightforward for the team since we had lots of practice forming up the basketball court last year. We are using 2x4s on the straight sections of trail and PVC board to form the curves. Our team placed formwork and the rebar cage for the bench in preparation for the first concrete pour.

Delivering concrete

Concrete is in the ground! Again. For the basketball court, a contractor completed the finishing, but the team will be pouring the benches and trail themselves!

Applying the finish

The trail consists of two different types of concrete finishes: exposed agregate and a broom finish. In this first pour, we displayed our skills at both! The bench shows off the broom finish, and the walking trail sections display the exposed ag.

Start again!

Now we are ready to start the process over again! The next few weeks on site will consist of a big delivery of trees, planting, and (weather permitting) many more concrete trucks.

Design work and mock-ups

On rainy days, we are continuing to make progress on the design of the bathroom. We are continuing to mock up and test design options. Our most recent mock-up was at the park, allowing us to look at the size and height of the pole barn pavilion.

The Start of the Home Stretch

Welcome back to the 18×18 House blog, summer edition!

Meagan and Julie with Detyrick

Temperatures have officially risen in Hale County, and the 18×18 House team has had several milestones in the past month. Drywall was installed, trees were planted, siding is going up, paint is on the walls…

First, at the start of the summer, the team had to say “See you later” to Naomi, who traveled back home to South Africa. But this isn’t goodbye! We hope to see her back before the project opening.

18x18 Team

Digging the Groundwork

Then Jake, Julie, and Meagan got going on planting trees around the house, which was more work than you might think! They needed holes much larger and deeper than their containers, and plenty of water to protect them from the summer heat. Thanks for the beautiful trees goes to Plantation Tree Company near Selma, who donated all four!

And some shenanigans were involved, as usual.

Jake watering tree

We also had a visitor this month! Thanks to Jake’s sister Ella, we were able to set and cover the French drains on site, to help control water flow around the house. French drain systems include perforated pipes that are buried with gravel, to keep water from pooling around the property. Ours will funnel water away from the eaves of the house and from the porch. And after we put her to work shoveling gravel in the summer heat, Ella will never come to see us again.

Siding! And a porch!

We also wrapped all four sides in battens and purlins, to which the siding will be attached. The strips of wood are going to hold the upper portions of our siding a couple inches out from the house, to make a shadow line and hide refrigerant lines from the air conditioning system. The eastern façade is the first one completed, and isn’t it satisfying?

Soon, the steel porch roof will be installed, which was fabricated for the team by Superior Metal Works in Newbern, and delivered to site. It’s a big part of the exterior of the house, so we were eagerly awaiting its delivery!

DRYWALL!!!!

Amongst all the work outside, the most exciting part of the month was the drywall installation! There’s a huge difference inside the house now, and we’re so happy to see how light fills the spaces. Painting started right away so that interior finish work can begin soon. That means taping a LOT of corners and using very long extension rollers to get to that double-height ceiling.

The light in the house with drywall installed is better and brighter than we could have hoped. How ’bout them windows?

The summer is passing in a whirlwind at the 18×18 House, and the opening is in sight! We’re going full speed ahead with finishes, inside and outside. Stay tuned to see the end of our story!

2,200 Holes and Counting…

Over the last couple of weeks, the Horseshoe Hub Courtyard team has continued to fabricate the screens in the shop, and are nearly done! After working on the shorter eight-foot screens, the team moved on to working on the nine-foot screens that are above the stage and near the main entrance, as well as 18-foot screens and corners. Thanks to the jigs that were fabricated, a small assembly line was created to facilitate making the screens as equally as possible. 

This past week the team finished cutting and perforating all the steel tubes for the footings, walkway strut, and wall plates and started welding the tabs to the wall plates. Also, a huge shoutout to Zane and Cassandra from Blackshop Birmingham for donating the laser-cut plates that make-up most of the walkway, they saved the team weeks worth of work!  

In other exciting news, the team took a trip this past Monday to Hunter Trees LLC and tagged the trees for the courtyard! Thirteen beautiful single trunk, Natchez Crepe Myrtles, which will be planted on site shortly after the screens are up.

Week 69

East facing elevation shows 18′ screens that slip past balcony datum line to separate the two elements. We are also working through options for the “porch” on the Southern portion of the site, we are interested in using lights or a dropped ceiling to lower the scale.

We finally modeled our most recent design! This past week we shifted from plans, sections and SketchUp to a physical model, so we could charette through the tree and furniture placement.

Stepping out of the waiting room looking towards the active space and porch.

Part of figuring out the tree layout is understanding how it shapes the north end, as another entrance to the courtyard as well as what it gives back to the street since it is the most public area of the design. 

Stay tuned as we work through the different options for the railing (not featured in model at the moment) and its interaction with the screens!