Howdy from the Moundville Pavilion team! The design has continued to evolve quickly throughout the past couple of weeks as they have been heavily focused on constructability and modifying the design of the columns. The team also got the chance recently to participate in Moundville Archaeological Park’s Knap-In, an annual stone tool makers event where visitors can learn about flint tools and how they’re made.

Columns and Ceiling

After the team clarified the design concept, new iterations of columns began to emerge that focused strongly on the overall intent of the project and its place within the site. The team looked at the columns in elevation, large-scale models, and renderings. 

An axon drawing of a column
Column plan and elevation
Connection between column and truss

In conjunction with the column design, the team has also been exploring ways to give tolerance to the ceiling assembly along with the method of attaching the finished surface material to the underside of the trusses. With the decision to deconstruct the current partially built pavilion, the team has the opportunity to realign the upper or lower ridges and two of the four planes that make up the form. Aligning the upper ridge allows for smoother and faster assembly of the direct-bearing roof structure and gives shelter during the construction of the ceiling. The team also decided to add lumber to the bottom cords of the trusses to align the two lower planes. The overall goal is to allow for the most efficiency and tolerance when reconstructing the trusses.

A drawing explaining the intersection of roof, ceiling, and a truss
A drawing looking at the details of the ceiling panels

Reviewing Executively

All of this work and response to recent guest reviewers culminated in an Executive Review, the event formerly dubbed “stress test.” The annual stress test examines each projects potential and feasibility to continue into the summer. Justin Miller (Head of the School of Architecture, Planning and Landscape Architecture), Rusty Smith (Rural Studio Associate Director), and Emily McGlohn (Rural Studio Associate Professor and leader of the 3rd-year studio) met with the team to see where the project currently is and where it is heading. 

The team presented their work at the Executive Review.

Rusty and Justin encouraged the team to consider an overlapping clip system for their ceiling and to see how we could simplify the design of the column to find a stronger balance between functionality and concept. At the end of the review, the team was challenged to build a full-scale mock-up of the final column design, complete with the roof structure, to show at the annual Pig Roast celebration at the end of the semester. 

Keep on Pushing!

In response to the feedback, the team is continuing to explore the column design, testing the suggested ceiling construction method, and mocking-up how the structure will be assembled. 

Check back soon to see where we head next as we begin to prepare for Pig Roast!