Myers’ Home team is on the run! They’re setting utilities, laying plumbing, and picking up materials as construction ramps up!

These folks had a review last week with Jake LaBarre to refine the building set contents. (Kudos to Riley, emerging expert in construction drawing formatting!) These are drawings that the team references during construction for just about everything. With updated documents in hand, they’re dodging rain and wind for spots of sun on site.

Power Trip
To power their saws, charge up those drills, and keep the tunes playing the team had to set up a temporary power pole. With Judith driving the trailer as Bobcat Delivery Girl and Madeline manning the joysticks on site, the pole was set and power nearly ready to connect.
Moving the pole from trailer to final location Mason directing pole placement Lifting the pole into the augured hole
Pipe dreams? Not so much.
Before the foundation slab can be poured, utilities are run, gravel leveled, and formwork is set. To begin work on utilities, more batter boards were constructed in order for the plumbing and electrical to be properly placed. These boards sit between the batter boards which mark the footprint of the home, they mark where pipes will emerge from the slab.
Riley and Judith driving batter board stakes into the ground
The team marked the utility lines on the tamped earth and began trenching for, first, plumbing and, above that, electrical conduit.
Marking the line for electrical conduit Trenching for the main drain Sloping towards the septic system
Next, they simultaneously begin dry fitting the joints and noting the lengths of pipe needed in the trench (cut a little long!). Throughout this they sloped the pipe in the trench and checked with the site level to ensure proper drainage.
Seal the deal
Following a successful drainage test, the team began assembling and gluing small length pipes, the shower run, washer, and toilet. After that, they dry-fit to the main drain. They triple-checked the pipes, marked for re-fitting, and primed purple. Finally, the team began sealing with the bright blue plumbing glue.

With everything in place, they began re-leveling and aligning the pipes with the position of future stud walls. As sunset approached the trenches were finally re-filled and the new utilities tucked in for the night.
Tamping the covered trenches Aligning emerging pipes to stud lines
One slab, comin’ right up!
The final steps before that long-awaited concrete truck’s journey to Newbern are gravel and formwork. The home’s footprint will be completed in two pours, one upcoming for the 24′ x 40′ interior, and another for the 8′ x 40′ porch slab.

In the coming days, the team will be cutting and setting the formwork for the slab and ordering gravel to level the area before the blessed arrival of sweet, sweet concrete. Hang tight to get the scoop! Over and out.