Howdy, folks. It’s time for another C.H.O.I.C.E. House roof raising roundup. Y’all know the drill, so let’s jump right into what we’ve been up to since our last post.

end of day site progress

It’s been a long time coming, but we are happy to finally report that trusses are up! Thanks to our friends working on Patriece’s Home and the expertise of “Crane Shane,” we raised all 25 trusses in one day. Everyone was pleased to see our 8:12 gabled roof make its way off paper and onto the streets of Uniontown as well as a first look at our big hit, the porch!

After truss day, we wasted little time moving right along to bracing and purlins. The bracing helps connect the trusses to each other and offers some more stability while sheathing the roof is in progress. Purlins are horizontal support beams that support rafters in the roof. We also installed hurricane straps as another layer of protection against future severe weather events.

Purlins were a multi-day adventure. For our readers looking to put up some purlins of their own, the process looks something like this. First, harness up (safety first!) Next, install the sub-fascia along the East and West ends of the units. Use the sub-fascia as the starting point for your first purlin. Make sure the purlins that are exposed under the eaves are painted gray before you install to ensure a coherent detail language. Alternatively, locate a younger student and hand them a ladder and a paintbrush. Begin moving up the roof! Adjust your harness as you climb. As you ascend, use the previously installed purlin as a step stool for placing the next one. Brace yourself against the wood to nail in the next 2×4. Take a moment to ask yourself: Why you didn’t wear knee pads? Finish nailing and make a mark for the next board at two feet on center. Repeat process until all purlins are installed.

On top of purlins, we also took some time to raise the trusses for the third volume with the help of Steve and the “Bob crane,” a.k.a. our Bobcat with a crane attachment. In the next few days, we’ll get the third volume sheathing going just like the roof of the main units.

Back at the main units, we’ve moved on to sheathing the roof. This team knows that the girls are capable of some tough stuff, so Hailey and AC have taken over the roof and turned it into a girls-only zone. Next time you see us, we’ll be dried in for winter, allowing us to frame up our interior walls without worrying about winter wind and rain. 

hailey and ac sit on roof

In the middle of all of this progress, we even took a day to dress up and check out the current 5th-year projects at Halloween Reviews. I guess you can say we think we’re hot (and spicy!) stuff.