excavation

Breaking News: We’re Breaking Ground!

This just in: there’s is a big hole in the Thermal Mass and Buoyancy Ventilation Research Project site!

Thanks to C & T Excavation Inc. the TMBV Test Buildings have broken ground. Local and Rural Studio excavation efficiando, Tyler, completed the initial site grading and the foundation dig. Let’s take a look at how the TMBV team prepped the site for this momentous day.

Newbern’s Newest Crater

plan view drawing showing batterboard arrangement
Plan of Batter Board layout, this drawing guided students in find the foundation limits

Before you can dig a hole, you’ve got to know where to dig! This is where the superheroes of construction, batter boards, come into play. Batter boards are quintessential for starting construction so they must be precise. To clarify, batter boards are temporary frames, set beyond the corners of planned groundwork at common elevations.

Typically, batter boards consist of two stakes driven into the ground with a horizontal member held between them. Next, once you’ve assembled and leveled the batter boards, you use construction string to “pull” layout lines. The layout lines are then secured to the batter boards. Layout lines cross the site either east to west or north to south, between batter boards, to indicate the foundation limits at their intersections. It’s important to note the elevation of the top of each batter board must match so when strings are pulled across the strings intersect.

The TMBV team pulled their first layout line west to east from the Supershed columns. From this line, all other layout lines are set. When all lines’ distances and intersections’ squareness are triple-checked, the team marked the initial grading limits on the ground with spray paint. The end result, with string crisscrossing about like laser beams, feels a bit like a scene from an action movie. Especially if you practice jumping over and rolling under the strings. But, of course, none of these very professional research graduate students took part in such conduct.

At the end of a long day pulling strings, the team marked their initial grading and detached all the layout lines from one side. The layout lines positions are marked on the batter boards so they can be put up and down as needed. Obviously, you can’t build with a bunch of strings in your way. After the initial site grading, the students re-pulled the strings which indicated the foundation limits, marked the corners, and Tyler began digging again. In about 6 hours time, Morrisette Campus had a brand new swimming pool and the TMBV team had a real project site.

Mock-up Progression

In parallel with site groundwork, the TMBV team worked across campus on their mock-up. To mimic the SIPs walls of the test buildings, the mock-up uses 2″ x 12″ stud walls. Due to the angle of the roof and the chimneys, there was much mitering to complete and even more mitering math to figure out. The team built all the stud walls and are ready to assemble. All the especially funky parallelograms you see below are the chimney pieces. With the kit of parts complete, the team awaits columns to build upon.

Cooling Porch Design

True to the design-build spirit, the team is still designing as they’ve started building. The ground plane of the cooling porch was the subject of this week’s design charrette. The team has used, concrete side-walk pieces they intend on using as pavers. However, it is not decided yet how those pavers are arranged.

The team wants to eliminate any excessive cutting of the pavers, especially exact cutting, so they ruled out a linear pattern. They are pursuing a mosaic-like pattern that minimizes concrete cuts. However, without a full inventory of all the concrete pieces, it’s difficult to produce a realistic design. Therefore, in the coming weeks, the team will be taking stock of their recyclable materials. After this, they can start laying out patterns using a steer skid loader to move concrete pieces around.

Welcome to Winter

a dirt roads lead to to silos both surround by frosted grass

As mentioned in the Thermal Mass and Buoyancy Ventilation Research Project Team’s last blog post, the chill has rolled into Hale County. There is never a shortage of beautiful scenery in these parts as proven by these frosty silos. By next post the TMBV team hopes to have another gorgeous view for you; a freshly poured foundation! Here’s hoping and thanks for tuning in!

Getting Dirty with the 3rd-Years

With the decisions made in studio, the 3rd-Years have finally broken ground on Ophelia’s 20K Home! That first means putting up badder boards, and then again, and again, and again …and again. In total seven times. Hey they want to get it right! 

With the exact points and measurement from the boards the team traced the plan of the foundation to the ground and measured where the footing would step. The students also said goodbye to a huge tree hanging over the buildable site, so here’s a quick thank you to the tree for it’s sacrifice. On Friday, the students had an online meeting with engineer Robert McGlohn for conformation and advice on of the proposed foundation changes and approval on the new porch detail.

Finally Tuesday was excavation day! The real fun began as the 3rd-Years got their shovels and cleaned up the hole for the foundation. The students then split into teams to create a quick process for creating the formwork for their concrete pour. Other students also worked on bracing the formwork, laying rebar, adjusting the badder boards (yes, again), finishing construction documents, digging holes for pier foundations, and filling in the smelly pool that formed at the low corner of the foundation.

With the formwork made and the rebar laid, the 3rd-Years are ready to pour concrete.