Last time we saw the 18×18 House team, they were putting shovels into the ground for the first time. Three months later, the project has leveled up!
The team first got their formwork ready for the concrete pour. This started with them digging their turndowns and trenches and then pulling strings, setting up formwork, and setting the plumbing pipes and electrical conduit.
The next step was putting down gravel, vapor barrier, and rebar. Then came the day everybody had been waiting for—the concrete pour! The team watched as Meagan cried tears of happiness when the slab was finally in place.
Once the slab was set, it was time to get to work. The team ordered and organized on-site to help them work as efficiently as possible.
Before the walls went up, the team laid down, some the termite flashing and sill gaskets to reduce air infiltration between the slab and the pressure-treated base plates.
After just two days, the exterior walls of the first floor were up and braced, then the team began to build and tilt up the interior walls from inside the house—a task that required lots of careful maneuvering due to its size.
They moved some scaffolding to the site and set it up around the house as to prepare to move upward.
Now the team is working on framing the second floor and building the stair. The joists have already been installed, and the team is gluing and nailing down the subfloor.
With the second floor platform installed, the team got a great view of the sunset down the hill, and they can’t wait to see that view from the very top. Stay tuned to see what the 18×18 House team does next!
You haven’t heard from the 18×18 House team in a while.
And they’ve been busy! Now officially “leftovers,” the squares graduated in early May, so everyone is feeling grown-up and very official. Pig Roast was a great chance for friends and family and visitors to catch up with the project, and for the team to explain the scheme of the house they were planning to build.
But then, everything changed…..AGAIN. Very recently, the 18×18 House was flipped on its head another time, with sleeping and bath on the ground floor and living and cooking elevated above. By cutting the third-story loft almost in half and extending it to the dormer, they found more usable space up there and vertical interest in the house. Now, the living room is below a balcony of sorts, and the loft has access to operable windows in the dormer. The team is pretty excited about making a double-height space happen in the living room, because the house now has a grand reveal when going up the main stairs.
At the same time, the mock-up has begun! The squares got their first shovels in the ground and poured their backyard slab for their doghouse-sized version of the project. Next comes tiny framed walls, sheathing, and cladding. Getting started with work on site is just around the corner!
It’s been a minute since you’ve heard from the Patriece’s Home team.
We last left them in the middle of their window installation, and since then they’ve finished! The fenestrations definitely gave the home its facial features and the wonderful Pella-donated windows filled the interior with beautiful light.
The team also installed the Pella-donated exterior doors. The doors have integrated windows to give the home even more exterior daylight and now the team can lock up the house when they leave for the day.
With such lovely natural light, the team met with designer Thomas Paterson of Lux Populi again to finalize a complementary artificial lighting plan. The group selected fixtures and bulbs that won’t attempt to replicate daytime light but give a different type of warm cast and task light for differing interior program.
With the stairs complete, it was easier for the team to bring tongue-and-groove plywood to lay the subfloor within their attic truss.
Once the subfloor was complete, the team could then finally finish their interior framing! The upstairs rooms have taken shape, and the team got very excited about the possibilities for flexible room at the top of the stairs.
They also put half-inch plywood along the interior walls of the stairs to later attach a durable layer of tongue-and-groove cypress boards. With a surface to cast light on, the team got even more excited about the exterior light from the windows at the top and bottom of the stairs.
With all the walls established, the group began looking toward wall fillers in preparation to enclose them with drywall (and with endless miscellaneous blocking).
We enjoyed installing the downstairs shower and upstairs bathtub base. From there, the team began fitting together the PVC drain, water, and vent system to the stub outs connections from the main drain in the concrete slab.
With the chunky PCV filling the walls, the group began routing flexible PEX tubing through the house. These water supply lines connect to their various fixture stub outs in the bathrooms and kitchen.
Then it was time for electrical boxes and outlets to find their place in the wall. With the supervision of some expert help, the team installed the two electrical units. These separate outlet boxes offer the opportunity for power to be individually accessed and maintained. With all the wire strung, the house is ready to be plugged into the meter on the temporary power pole outside. Just like decorating for the holidays. We might as well: the house is already green.
Speaking of holidays, Soup Roast snuck up on the team so fast! The four tidied up for the visitors and started the special day’s project tour with a quick presentation of their home. The crowd got to wander around the home. It’s safe to say it was well received!
The team has a lot to be thankful for in their second holiday season at Rural Studio. The opportunity to build, the wonderful community that supports them, delicious food, and a home now ready for insulation and drywall! Check back here in the new year for more big updates on Patriece’s Home!
It’s curtain call on the Myers’ Home, construction that is. The team wrapped up just in time for the holiday season and towed away the trailer and all. The keys have been given to the clients. The team can’t wait to hear how the house functions in action. But how about a dive into those last few weeks on site in Newbern?
Flex Walls, Finally
One of the primary aims of the Myers’ Home was to provide a formwork for varying generation needs. The team explored this concept by building the “shell” house with no spatial divisions outside of the “core” volume. With this method, a client could hypothetically walk through the full-scale model of the home. With full experience of the space, they can decide where they’d like bedroom divisions from several schemes.
South wing – view East
South wing – view Southwest
North wing – view Southwest
View North to South
North wing – view Northeast
These “flex walls” are stud walls constructed in place, rather than tilt up, and anchored with a few masonry screws. They are paneled with sanded and primed plywood and fasteners are entirely visible. These details allow the walls to be more easily altered or removed years down the road. If the family is in need of a new room configuration, these walls can handle it.
Framing the flex wall
Paneling in plywood
Primed bedroom flex wall
Bits and Bobs
Of course, at the end of every building project there is what’s called a “punch list.” It’s a list of the remaining tasks to ready the house for turnover. On this list for the Myers’ Home was a few coats of finish to the butcher-block countertops, making the stair handrail, caulking the last of corners, tightening up door hardware, and sealing the interior and exterior slabs.
Porch Conclusions
Another final task was to complete the lower row of siding on the front exterior face of the home. A quick task that certainly visually completes the house quickly!
One row left!
With all bents in place and secured, we begin raising and securing purlins. Then, we welded the purlin mats at the same time as the bents and installed them as single units by bay. Riley took the reins and began welding up a storm while the others clamp and shimmy the pieces to level.
Finally, we wrapped up the roofing, a quicker job than expected. After just a day and a half the team completed the final line of siding and the porch roof. The panels went on with slightly more precision than the main roof. The tapping screws needed to catch the 1-1/4″ purlins, so measuring and pre-drilling of the sheets and purlins were required.
With a final coat of sealant to the interior slab and porch pavers, the house was ready for move-in!
That’s a Wrap
Madeline, Judith, and Riley are on to new endeavors, though questionably bigger and better than this one.
Start spreadin’ the news! Riley is kicking it in the Big Apple, starting work at MADE Design/Build in Brooklyn, NY. With an in-house woodshop and IKEA next door he’s sure to be up to his ears in miters and meatballs.
Judith is sticking around Newbern and joining the teaching team as 3rd-Year Instructor/Coordinator. She’ll be working on Rosie’s Home with Emily McGlohn and the new batch of 3rd-year students. Hale County just can’t seem to shake her off!
Madeline has hit the road to Bozeman, MT, where she’ll be working at Minarik Architecture. She’s pleased with her new snowboarding opportunities and excited to get into conscious and contextual residential work. Stay thawed up there!
The team could not be more grateful for the support of Rural Studio faculty and staff, student colleagues, consultants, donors, and friends. It’s not goodbye, it’s see you later. This is the Myers’ Home team signing off.
The Myers’ Home team has made it to the top layer of finishes. Almost every material and layer they apply at this point is completely visible and the finish surface in the home. So they’re watching their step with the mud and taking some extra care in details.
Painting the Day Away
After sheetrock is complete, the team and their helpers scrub up the drywall mud and prepare to begin painting. While the home’s core, outer walls, and to-be-built flex walls are designed using different materials, they’ll all be painted white to reduce noise. It also provides a clean surface, should the homeowner want to paint it to personal preference.
a good mopping for Myers’ Home
Thanks to the 5th-Years!
Madeline prepping to paint
Tongue and groove seams take some extra care
The sheetrock is the cleanest surface on the outer edges of the home. It contains most electrical for the possible rooms and is more workable for openings like windows and doors. The board surface on the home’s core—the kitchen, bath, and stair—is a durable tongue-and-groove board. These surfaces are interacted with more often and need added durability. The flex walls that partition bed and living space will be plywood, and primed white. These walls will be anchored in only a few points should the home configuration need to change years down the road.
Just a Trim, Please
Sanding upper trim in the kitchen
Installing trim around the south window
Once the walls have their first coat, trim can be installed around the whole house. As materials change, so does trim design strategy. The baseboards run along sheetrock surfaces, and where board material begins, the trim moves to the top edge of the ceiling. Windows are trimmed out on their edges.
Last Call on Windows
Speaking of windows, all of the custom window units are installed and Riley is adding the last few components post-install. Each of the operable and fixed windows get their own trim box, also constructed of cypress. These are taped off and kept natural as the last coat of paint is applied to the surrounding wall.
Riley installs backer rod to seal window gaps
The window in the last stages of paint
The wall wash detail in the shower, lovely morning light!
Steel-Clad Sensibility
Meanwhile, the exterior of the house is getting the full treatment. Siding is starting to be installed on the two gable ends and back of the house. The lower twelve feet of front face will be clad after construction of the porch slab. This prevents siding from being dinged and damaged during concrete pours and metalwork. The porch structure will then be used as a platform to finish the top few feet of siding.
However, the installation process is straightforward for the other three sides. Panels are pre-drilled with screw holes, openings for windows and vents are cut, if necessary. Then the panels are moved into place, overlap length checked, and screwed in from overlap edge over. This prevents most bubbling in the panel as the lines of screws progress over.
Riley manning the boom lift
Making cuts for the gable angle
The backside of the home
South face siding with a sneak peak of the porch footprint!
The Thermal Mass & Buoyancy Ventilation team has also kindly lent their rental boom lift. The Myers’ Home team is using this lift to install siding high on the gable ends. It’s certainly a much smoother route than multi-story scaffolding! They also used it to install the last few pieces of flashing around windows. The flashing details on this house are in the same family as those used on the roof. To maintain the tight shell, window openings are designed to be sharp and clean.
On Deck
The team is now on their last big push for the interior. They’re building flex walls, preparing for stair treads, painting cabinets, and making the rounds on finish electrical and plumbing. Soon, all lights will be on and water will be flowing!
The kitchen space; here come the cabinets!
Bedroom/living area pre-flex wall
On the outside, these folks are on standby for porch plans. Imminently, they’re headed up the road to Birmingham for some porch fabrication. This means steel cutting, drilling, and welding! Before that they’ll be boots in the mud again digging for the footings and pavers of the porch. More on that soon, thanks for keeping up!
Swamp Sunflowers are blooming at Myers’ Home!
Riley, Judith, and Madeline in their new medicine cabinet