This Summer has flown by for the C.H.O.I.C.E. House team. Good news! We’re officially up and out of the ground! A few rainy weeks put block laying on the back burner, but thanks to local mason James Harris, we’ve raised the slab (and the roof will soon follow)!


While block laying was in progress, we continued working on the third volume. The main house units are built on an elevated slab foundation, but the third volume is designed to be on a slab-on-grade foundation, so no need for any concrete blocks. With the help of a few of our fellow “leftover” students, we knocked out the small slab pour in under an hour and got it finished up and ready to frame.





Building the small walls of the third volume was a great way to knock the dust off of our framing skills before we tackle the main units. With the help of professor Steve Long, and a much appreciated guest appearance from our colleague Caitlyn, the walls were up and braced in a morning. Framing the third volume first was also a great way to test our strategy for connecting the porch header to the wall. It looks like the “notch” in the framing was successful! Soon, we’ll assemble the third volume’s column and header to test the entire detail assembly, almost like a second mockup!

Now that the CMU walls are up, we also backfilled the footprint of the units with dirt. Next up is setting up plumbing, adding a layer of gravel, building some formwork, and then we’re off to the races for our final concrete pour!


Until next time, we’ll be keeping our hopes high and our trenches dry.