Author: Amanda Kaase

3, 2, 1 Lift Off!

As astronauts were headed for the moon, the Smith Park team was also reaching for the stars—if reaching for the stars means pouring concrete and planting trees! The second half of the spring semester was a productive one for Smith Park. We expanded our horizons beyond just trees and concrete to include work on gravel courtyards and chain link screens.

Captivating new images

Get ready to see Smith Park from a new perspective. The park recently had a photoshoot with a drone thanks to Christian Ayala with the Front Porch team. It might not be as impressive as seeing the earth from the far side of the moon, but it feels just as exciting for the team! We’re thrilled to continue tracking the construction process from this bird’s eye view.

Construction progress

The trail is fully excavated! When you take a walk around the park, you can see how all of the pieces of the trail will come together—although the sections of road base look more like a walk on Mars than on Earth.

Over 50% of the of the concrete for the trail is finished. One continuous section of concrete trail surrounds the field and connects to the basketball court. The second section starts at the gravel courtyard by the pavilion and links up to the second bench. For a more detailed look at this process and the tree planting process, check out our last blog.

Tree launch window

How do we decide what trees can be planted and which ones need to wait? The sequencing is important because we need space for large concrete trucks to enter the site without driving over our freshly planted trees. Therefor, in most spaces, we must pour concrete before we can plant trees. The challenge is making progress on the trail quickly enough to plant within the “launch window” or planting season. So far, the weather has been on our side, but we are still racing against the summer heat to get as many planted in this season as possible. Over 50 have been planted so far with the help of our peers. Fellow 5th-year, leftover, and 3rd-year students came out to the park and helped to plant 10 trees in one morning. Thank you to the student organization and all the students who came out to help!

Black gum trees surround the field, and crepe myrtle trees shade the pavilion’s courtyard space. Our “mosaic” plating strategy uses sugar maple, trident maple, and river birch trees to create shady spaces around the park.

Exploring a new frontier

Chain link screens are starting to go up around site. We set the poles for the field backstop with concrete, and we are looking to install the screens in the coming weeks. The chain link screens will be hung vertically (a detail borrowed from Lions Park) to allow for the height of the fence to change. On the field, the sweeping arc of the backstop is taking shape. The next steps will be to attach the top rail that the screens will hang from.

Work started again on the mock-up at Morrisette finishing out the chain link screen. To give the screens around the basketball court some dynamic movement we changed the shape of the end bays. Instead of setting all of the poles plumb and vertical, the end poles terminate into the ground at an angle, creating a shape similar to a sail. Check out the awesome renderings on the Smith Park webpage for a closer look at the chain link screens! This unique detail at the ground is what we were testing with the mock-up. We are also working through how to cut and secure the chain link screen when it is hung at such a steep angle. The mock-up proved that it is possible to achieve the shape we want and we can further test how to assemble the screen in a way that gives it the most durability.

Design updates from Mission Control

The design for the bathroom is becoming even more refined. After meeting with Rural Studio consultants, Susan Rodriguez and Charlie Lowrey, we made subtle changes to the entry sequence and simplified the roof. We are working through details for the roof fabrication The bathroom site is currently being prepped for plumbing and foundation work. As more details are falling into place, we are now able to further explore the graphic identity of the park.

That’s all for this mission! Report back in T–minus a few months for a progress report from the summer.

Tree Talk—The Smith Park team is developing green thumbs

An update on the basketball court, planting trees during neckdown, and pouring the first section of the walking trail.

Where we left off

Last year we prepped for the holidays by installing the basketball court at the park. You can read about how we prepared the formwork and installed the hoop posts in our last blog. Since then, we’ve applied a burlap finish to the court and cut all the control joints. A design is also in the works for a graphic painting on the court surface—something playful, colorful!

An overview of the order of—PEMDAS

Our project site is 2.5 acres, and we are touching almost every foot of it. That is a lot more square footage than a house! A big design challenge for us in recent days has been the staging and sequencing of construction. We are balancing tree delivery and installation, concrete pours, and more. To walk our readers through the order of events, we can apply a familiar algebra anagram PEMDAS.

Planting trees

The winter months are planting season, and we are looking to plant 115 trees at the park! Our goal is to get them in the ground before the weather gets too hot, so planting is our first priority. The first batch to be planted included seven black gum trees and three willow oaks. Lots of people helped during “Neckdown” Week , our time to maintain properties and make big project pushes. These helpers included our friends in Auburn University’s Landscape Architecture Program, all with their aid, 10 trees were installed in a little over a day!

Excavating the trail: Part 1

After we planted the trees, our friends at C&T Excavating came back and helped us with the excavation and base work for the first section of walking trail. Excavation for the trail is being divided into three parts. This strategy maintains truck access for concrete and tree deliveries while keeping the working area at a more manageable scale.

Make formwork

This part was pretty straightforward for the team since we had lots of practice forming up the basketball court last year. We are using 2x4s on the straight sections of trail and PVC board to form the curves. Our team placed formwork and the rebar cage for the bench in preparation for the first concrete pour.

Delivering concrete

Concrete is in the ground! Again. For the basketball court, a contractor completed the finishing, but the team will be pouring the benches and trail themselves!

Applying the finish

The trail consists of two different types of concrete finishes: exposed agregate and a broom finish. In this first pour, we displayed our skills at both! The bench shows off the broom finish, and the walking trail sections display the exposed ag.

Start again!

Now we are ready to start the process over again! The next few weeks on site will consist of a big delivery of trees, planting, and (weather permitting) many more concrete trucks.

Design work and mock-ups

On rainy days, we are continuing to make progress on the design of the bathroom. We are continuing to mock up and test design options. Our most recent mock-up was at the park, allowing us to look at the size and height of the pole barn pavilion.

Where’s my water?

“Where’s my water?” It’s at Smith Park!

Amanda making a rainbow with the water hose

The team officially got the water line installed on site just before taking off for Thanksgiving Break. We had to give our devoted readers a sneak peek of the most recent developments for the project, but now lets back up a few weeks and talk about our fa-boo-lous Halloween!

October—It was groundbreaking!

Ground was officially broken at the park at the end of October. With help from Tyler from C & T Excavating and a few of his little toys, we completed the rough grading and first phase of excavation. The play mound is also beginning to take shape as the excavated dirt is building up. John, the teams self-elected Bobcat operator, could not have been happier watching the pros at work in the big bulldozer.

The team went through a Freaky Friday experience at the Studio’s annual Halloween Reviews when they accidentally swapped bodies with the Dining House team, dressing as one another!

Never fear, though. Everyone has since recovered. Well, almost everyone: the team is still convinced that Trenton’s hair leans more platinum than blond since the switch.

Our third community meeting

With construction picking up pace, the team wanted to share the full design with the community. We held a meeting at the armory with community members, the parks and rec board, and the cities newly elected mayor in attendance.

Can money grow on trees?

The short answer is still no. However, the Smith Park team has good news: we were awarded not one, but two additional grants! These funds will go towards a new bathroom and trees for the park. A $5,000 grant was awarded by the R C & D Council to partially fund the parks new permanent bathroom. Alabama Power Foundation’s Good Roots Grant awarded the project $1,000. We are looking forward to starting work to plant trees and build a bathroom in the new year.

Speaking of trees

Two of the team’s tree huggers went on a shopping spree at the local nursery. They tagged some beautiful specimens, including these beautiful black gum and maple trees – can you spot the ones we tagged? In all, 120 trees were tagged between Plantation Tree Company, located in Selma, and Green Valley Trees, in Montevallo,  AL.


What you need to install a basketball court?

No.1: Water

In the process of trenching the lines Meghan found a new favorite machine: the Ditch Witch trencher. With her trencher magic, we installed all four of the in-ground water boxes and tied them together with PEX crimp-ring piping. Now over half the park has running water, perfect for mixing concrete, cleaning dirty boots, or making rainbows.

No.2: Concrete

No.3: A crane?

Yes, you do need all these things to construct a court! Ok, the crane might be optional, but it sure did eliminate a lot of heavy lifting. To prepare for pouring the concrete footing for the backboard pole, the team designed and built bracing. This approach kept both poles aligned and plumb while the concrete was setting.


Happy Holidays everyone!

Our next step for the court will be to get the slab poured. It’s on our Christmas wish to get the work done before the holidays. Be sure to check out our next blog, where you’ll learn how many concrete trucks it takes to fill a basketball court!

Before you go… If anyone is feeling generous this holiday season, the Smith Park team would like to leave you with this—our Christmas List:

  • A basketball (for Trenton and John)
  • An extra sledgehammer (our most used tool)
  • T-25 drill bits (for Amanda)
  • Lastly, a pair of tented safety glasses (for Meghan because John “borrowed” hers)