concrete

Tree Talk—The Smith Park team is developing green thumbs

An update on the basketball court, planting trees during neckdown, and pouring the first section of the walking trail.

Where we left off

Last year we prepped for the holidays by installing the basketball court at the park. You can read about how we prepared the formwork and installed the hoop posts in our last blog. Since then, we’ve applied a burlap finish to the court and cut all the control joints. A design is also in the works for a graphic painting on the court surface—something playful, colorful!

An overview of the order of—PEMDAS

Our project site is 2.5 acres, and we are touching almost every foot of it. That is a lot more square footage than a house! A big design challenge for us in recent days has been the staging and sequencing of construction. We are balancing tree delivery and installation, concrete pours, and more. To walk our readers through the order of events, we can apply a familiar algebra anagram PEMDAS.

Planting trees

The winter months are planting season, and we are looking to plant 115 trees at the park! Our goal is to get them in the ground before the weather gets too hot, so planting is our first priority. The first batch to be planted included seven black gum trees and three willow oaks. Lots of people helped during “Neckdown” Week , our time to maintain properties and make big project pushes. These helpers included our friends in Auburn University’s Landscape Architecture Program, all with their aid, 10 trees were installed in a little over a day!

Excavating the trail: Part 1

After we planted the trees, our friends at C&T Excavating came back and helped us with the excavation and base work for the first section of walking trail. Excavation for the trail is being divided into three parts. This strategy maintains truck access for concrete and tree deliveries while keeping the working area at a more manageable scale.

Make formwork

This part was pretty straightforward for the team since we had lots of practice forming up the basketball court last year. We are using 2x4s on the straight sections of trail and PVC board to form the curves. Our team placed formwork and the rebar cage for the bench in preparation for the first concrete pour.

Delivering concrete

Concrete is in the ground! Again. For the basketball court, a contractor completed the finishing, but the team will be pouring the benches and trail themselves!

Applying the finish

The trail consists of two different types of concrete finishes: exposed agregate and a broom finish. In this first pour, we displayed our skills at both! The bench shows off the broom finish, and the walking trail sections display the exposed ag.

Start again!

Now we are ready to start the process over again! The next few weeks on site will consist of a big delivery of trees, planting, and (weather permitting) many more concrete trucks.

Design work and mock-ups

On rainy days, we are continuing to make progress on the design of the bathroom. We are continuing to mock up and test design options. Our most recent mock-up was at the park, allowing us to look at the size and height of the pole barn pavilion.

Four Cores and Seven Weeks Ago…

Student lying down on wooden framed box.

The CLT Core House team had just begun their journey to build the core mock-up. Bright-eyed and eager to prove their design’s worth, they got to work. Despite the heat, it was exciting for them to be working outside.

They exclaimed, “Finally, we can get our hands dirty!” Though they, like many before them, were about to see an entirely new side of design, one that would transform their drawings into reality and expose the previously missed shortcomings. A humble lesson for all, and perhaps the most potent. Yet the team treated these lessons as opportunities, not an embarrassments, and were pleased to embrace them.

How optimistic! How youthful!

The act of, as it were, “mocking up” a design is a pivotal moment for any builder, green or experienced alike. It forced the CLT Core House team to reckon with the stutters in their meticulous design process. No matter how long the process took, they learned new lessons. One would think that after the third consecutive day of sanding wood, they might have stopped to question the process. Alas, they powered through for the fourth, and yes, fifth day of sanding.

How determined! How youthful!

Once the students realized that sanding one spot means sanding all spots, they came to their senses and scrapped the sanding altogether.

Do not fear, dear reader: not all lessons were born of mistakes. Many a wise word was gained from consults versed in all manners of design. Among these travelers came Joe Burns of Chicago, the city of winds, to aid our CLT Core House team in structural matters. He continually adds merit to their work, ensuring that their uncommon use of shiplap as both a ceiling and structural member effectively transfers shear loads from walls to the central core as intended.

Many more came bearing gifts of knowledge and advice. Jonas Weber of David Baker Architects, defender of tile, Kiel Moe and Jacob Mans of various wooded landscapes, and lady Adele Schirmer of all things civil (engineering) have helped to refine the details of the cores themselves and the performance of the house. The CLT Core House team is so appreciative of this aid, not forgetting the many more who have helped take this project to where it is.

A model representing the bathroom core's tile and CLT.

How Fortunate!

Soon they will endeavor to build on a full scale. They do seem to feel as though they are ready…

How Ambitious! How Youthful!

Students demonstrate the layout of their mock-up.

Curb Alert!

Hello again and welcome back to the newest addition of the Rural Studio Bathhouse blog! We are so thrilled to show everyone what we’ve been up to recently! We have a big concrete update, but first—we’ve started stacking our wood walls!

student team poses in outdoor shower
Progress on the outdoor shower!

This is super exciting because this is the major focus of the project, and will be the finish wall material in most of the spaces. Continuing with the construction of the outdoor shower, we have started the stacking here. With the help of the jig table that we built a few months ago, we can align our pieces of cypress wood on one side (the interior of the building) and can clamp them down to the board below, creating a uniform module of five pieces.

We are assembling the modules in the Fabrication Pavilion so we can have a clean working surface. This allows us to stack the modules as they will be set up on site, get everything square and level, and then move the modules in place on site.

We have just a few more layers of modules to assemble and then will begin the process of drilling the holes for the threaded rods in each module.

image of a corner of the stacked outdoor shower
Box-joined corners

As the stacking of the outdoor shower walls was taking place, we also began the process of pouring the concrete curbs around the perimeter of the outdoor shower. We marked the curbs on the slab, assembled framed walls in place on the slab to hold the plywood formwork, and then leveled and attached the plywood to the formwork frames. Next, it was time for the pour!

image of interior curb formwork
Outdoor shower curb formwork

With the assistance of some great helpers, we were able to form a wheelbarrow and bucket brigade, lifting the concrete up into the curbs in the outdoor shower.

After two days, we were able to remove the interior formwork and the vertical formwork walls on the exterior, revealing the hefty slab and curbs!

Once we saw how the pour went for the outdoor shower, we used the same process to build the curb formwork for the toilet and shower pods.

Pouring the outdoor shower first did teach us some things, including how to attach the plywood to the frames and the need to account for gaps at the seam between the formwork and slab due to the leveling process, and generally we learned the overall process of getting the concrete into the curbs.

After caulking all gaps, the formwork was set and it was ready to pour!

image of finished curb formwork on toilet and shower pods
Before the pour

Again with the help of some fantastic helpers, we recently poured the curbs for the toilet and shower pods and are so excited to almost be done with concrete!

image of toilet and shower pod right after concrete pour
After!

As this is being written, the team has been taking off all the interior curb formwork and the exterior vertical walls on the toilet and shower pod, revealing the slab and curbs!

We have another concrete pour coming up in a few days. This next pour will be for the foundation of a gray water filtration system for the outdoor shower run-off and the foundation of the bottle-filling station at the front of the building. We are already busy preparing for that pour with more digging and more rebar! Afterward, the only concrete left will be a topping slab going into each of the existing pods (the laundry and getting ready pods).

The team is very excited about the progress being made and cannot wait to dive back into the assembly of the wood walls for the outdoor shower and the rest of the building!

students take a rest in outdoor shower
Time for a nap!

Thanks for following along with the Bathhouse blog! We look forward to providing another update very soon.

– Rural Studio Bathhouse Team

Carla, Ambar, Ashley, and Logan

Taking a Slab at It: A Bathhouse Concrete Story!

Hello dearest reader and welcome back to the latest edition of the Rural Studio Bathhouse blog!

The past few months have been a very exciting and productive period for the Bathhouse. We are very happy to share what all we’ve been up to since we last spoke!

Students pose for picture on metal deck

At the time of our last update, we had just finished all the underground plumbing and preparing the CMU foundation walls for the floor structure.

We picked up on site where we left off by moving the structural beams into their places in the foundation walls and securing them in place!

View of students looking over metal deck from below
Greetings, Earthlings!

After cutting our metal decking to size, we were able to place the decking and began securing it to the CMU walls. Our good friend, Shane, helped us out by welding the decking down to the beams.

Once the deck was in place, it was time for Spring Break, but we did not take a break from the project. We had a very relaxing week in the woodshop building all the modular formwork for the slab!

Student screws pieces of wood together
Assembling base module supports

Once it was all built, we got busy on site installing the formwork. We started off with ledger boards on the CMU walls, then installed the base support modules and plywood base, and finally pulled strings to set the upright walls in place. We then braced these walls back to the base and added plywood to the inside face, completing the formwork.

image of completed formwork
Finished formwork

When the formwork was set, it provided a nice square base to measure all the penetrations in the slab from. We started off with the holes for the threaded rods.

Next, we marked out all the electrical and plumbing penetrations in the decking and cut them out.

While all of this was going on, we also began plumbing the whole Bathhouse and installing all the electrical conduit and boxes in the crawlspaces. While plumbing was occurring, rebar was being cut to size on the ground. We used bracing attached to the formwork walls to help support the PVC sleeves for the threaded rods and the plumbing and electrical stub outs.

After all the plumbing was completed and tested, we were able to begin putting the rebar reinforcement into place.

The team tied all the pieces together to form a large rebar mat for the slab. With the rebar in place, it was time to add in the last thing, metal mesh, which helps prevent cracking within the slab. The team finished this final step just in time to celebrate at Pig Roast!

We had a great time on Friday night of Pig Roast weekend listening to all the alumni lectures and really enjoyed getting to show off our project and the progress we have made to all our friends and families on Saturday. We finished the day off with an evening of festivities, great food, and wonderful live music.

The team speaking with former Rural Studio student
The bathhouse team meeting and looking at construction photos with original Supershed and Bathhouse team member, Jacqui Hart!

After a weekend of fun, it was quickly back to work for the bathhouse team! First thing Monday morning we got Concrete! An excellent team from JM concrete in nearby Uniontown made quick work of the pour and did a fantastic job with the finishing.

team posing with thumbs-up for concrete
Thumbs up for concrete!

We are so proud to have the heart of the project completed!

As she stands now

We are so happy to share the huge amount of progress being made! Next, we will be preparing to pour all the curbs under the timber walls and beginning the process of stacking the timber modules for the walls.

The team poses in front of project

Thanks so much for reading along and we hope to provide another exciting update very soon!

– Rural Studio Bathhouse Team

Carla, Ambar, Ashley, and Logan 

Leveled Up

Last time we saw the 18×18 House team, they were putting shovels into the ground for the first time. Three months later, the project has leveled up! 

The team first got their formwork ready for the concrete pour. This started with them digging their turndowns and trenches and then pulling strings, setting up formwork, and setting the plumbing pipes and electrical conduit.

The next step was putting down gravel, vapor barrier, and rebar. Then came the day everybody had been waiting for—the concrete pour! The team watched as Meagan cried tears of happiness when the slab was finally in place.

Once the slab was set, it was time to get to work. The team ordered and organized on-site to help them work as efficiently as possible.

Before the walls went up, the team laid down, some the termite flashing and sill gaskets to reduce air infiltration between the slab and the pressure-treated base plates. 

After just two days, the exterior walls of the first floor were up and braced, then the team began to build and tilt up the interior walls from inside the house—a task that required lots of careful maneuvering due to its size.

They moved some scaffolding to the site and set it up around the house as to prepare to move upward.

Now the team is working on framing the second floor and building the stair. The joists have already been installed, and the team is gluing and nailing down the subfloor.

With the second floor platform installed, the team got a great view of the sunset down the hill, and they can’t wait to see that view from the very top. Stay tuned to see what the 18×18 House team does next!