neckdown

Tree Talk—The Smith Park team is developing green thumbs

An update on the basketball court, planting trees during neckdown, and pouring the first section of the walking trail.

Where we left off

Last year we prepped for the holidays by installing the basketball court at the park. You can read about how we prepared the formwork and installed the hoop posts in our last blog. Since then, we’ve applied a burlap finish to the court and cut all the control joints. A design is also in the works for a graphic painting on the court surface—something playful, colorful!

An overview of the order of—PEMDAS

Our project site is 2.5 acres, and we are touching almost every foot of it. That is a lot more square footage than a house! A big design challenge for us in recent days has been the staging and sequencing of construction. We are balancing tree delivery and installation, concrete pours, and more. To walk our readers through the order of events, we can apply a familiar algebra anagram PEMDAS.

Planting trees

The winter months are planting season, and we are looking to plant 115 trees at the park! Our goal is to get them in the ground before the weather gets too hot, so planting is our first priority. The first batch to be planted included seven black gum trees and three willow oaks. Lots of people helped during “Neckdown” Week , our time to maintain properties and make big project pushes. These helpers included our friends in Auburn University’s Landscape Architecture Program, all with their aid, 10 trees were installed in a little over a day!

Excavating the trail: Part 1

After we planted the trees, our friends at C&T Excavating came back and helped us with the excavation and base work for the first section of walking trail. Excavation for the trail is being divided into three parts. This strategy maintains truck access for concrete and tree deliveries while keeping the working area at a more manageable scale.

Make formwork

This part was pretty straightforward for the team since we had lots of practice forming up the basketball court last year. We are using 2x4s on the straight sections of trail and PVC board to form the curves. Our team placed formwork and the rebar cage for the bench in preparation for the first concrete pour.

Delivering concrete

Concrete is in the ground! Again. For the basketball court, a contractor completed the finishing, but the team will be pouring the benches and trail themselves!

Applying the finish

The trail consists of two different types of concrete finishes: exposed agregate and a broom finish. In this first pour, we displayed our skills at both! The bench shows off the broom finish, and the walking trail sections display the exposed ag.

Start again!

Now we are ready to start the process over again! The next few weeks on site will consist of a big delivery of trees, planting, and (weather permitting) many more concrete trucks.

Design work and mock-ups

On rainy days, we are continuing to make progress on the design of the bathroom. We are continuing to mock up and test design options. Our most recent mock-up was at the park, allowing us to look at the size and height of the pole barn pavilion.

“Neckdown” Week: Planting trees, planting our feet, using our hands

Another “Neckdown” week ended in success! Neckdown is where the entire student, faculty, and staff help out in the community by doing fix-up jobs. Everyone gets down into the dirt and jumps in the ditch. No project is too small or too big, and we have lots of hands.

This semester, the Studio worked on a multitude of projects both on and off the main campus. While the Morrisette House was getting cleaned top to bottom, the Fabrication Pavilion was getting some new structural fasteners put in the trusses and columns to prepare for a new roof. The Farm installed new planter beds over Christmas break, so we got them up and running with dirt and seeds.

Meanwhile, some of the crew helped the CLT Core House plant trees and do some last-minute cleaning. Trees were the order of business elsewhere, too: We helped both the Dining House team and the Smith Park team plant trees. And we gave both teams a hand milling lumber.

We also accomplished other tasks at our local parks. At Perry Lakes Park, we replaced walkway boards. At Lions Park, we repaired bleachers, fences, and the concession stand, and we rebuilt the gate and gave it a fresh coat of paint. You would never guess who helped rebuild the gate: our fabulous alumnus Zane Morgan of Blackshop in Birmingham, Alabama.

A shout-out to David Hill, who brought out landscape architecture students to plant trees and care for other parts of the landscaping.
All in all, the spring Neckdown week was productive, and the Studio is ready to get back to work on the projects at hand!

Transitioning: A successful summer into a fruitful fall

A perspective of the north and west elevation.

As summer rolls into fall, we are continuing to work toward completing our project!

In our last blog post, we had recently gotten “dried in” and were beginning to work on flashing, as well as mechanical, electrical, and plumbing. Since then, we have made lots of progress and are thrilled with how things are coming together.

A photo of the north elevation of the core house.

Our resident electrician, Sarah, has been hard at work running wires and installing everything in our mechanical / laundry space!

After putting insulation on the roof and flashing on the exterior, we made a big pish, putting up our corrugated metal siding. The details all required careful thought and planning: aligning screw spacing, cutting out for openings, and considering how to apply the metal panels to the roof and walls. It was rewarding to see our layers of effort enclosed and finally finished.

At the end of August, we officially completed putting up our metal siding!

The view of the core house from the neighbor's driveway.
HIP HIP HOORAY!

After metal was complete, it was time for “Neckdown Week,” the time when we focus on upkeep and cleanup. We had many amazing helpers! We safely put away all of our scaffolding. We moved our insulation into the house in preparation for insulating in the coming weeks. And we dug trenches, every helper’s favorite task!

We got our main water line trenched and connected, so we now have water on site!

We also dug trenches and spread gravel to prepare for pouring the concrete for our porches.

Students dig the turndown for the front porch.

The team worked on formwork, vapor barrier, and rebar to prepare for the pour as well. Then, we poured our concrete and finished it, exposing the aggregate. We are so excited to have the porch concrete done. The porches have proven to be lovely spaces, and the front porch is even one team member’s favorite room in the house.

Now we are working on installing our exterior and interior doors, as well as final plumbing and electrical connections. We also grouted the tile in the bathroom recently and are thrilled with the finished look.

Next up… insulation, then shiplap! Until next time!

Did You Hear About Our New Shovel?

Smith team at the pole barn

It is ground-breaking!

We’ve been doing great and we are so excited to show you where we’ve been since December.  

Unearthing our potential 

Since we last sent an update your way, a lot has changed. After the Soup Roast review, we took our winter break to not only relax but also to dive headfirst into the world of project budgeting. We wanted to better grasp the costs of our proposals and learn what we can and cannot do based on those numbers. This exercise has allowed us to explore a variety of new, and returning, options for play, landscaping, and park infrastructure with a higher level of focus. 

Enough money talk! With some refined eyes, our designs have taken major steps forward as well, especially with the park’s major infrastructure. We’ve chosen material for the parking areas, the walking trail and the basketball court along with their dimensions, orientations, and placements on the site. The next step is easy: figure out how to do it!

This project rocks

Along with the budgeting, material selection, and site placements of the new infrastructure pieces, the team began our first phases of site work in mid-January. To begin working on the park’s site, we had to prepare it by removing a lot of the existing infrastructure, including perimeter and baseball field fencing, the existing basketball surface, the field light poles, the baseball dugouts, and numerous others. 

Over the course of a week, the team, along with some helpers, was able to completely transform the park into a whole new space. While it might look a bit bare, we have big plans for it coming very soon!

Sowing the seeds for success

Now that the park has undergone its first phases of clean up, we have been moving right along with the project’s design and details. Since January the team has had the opportunity to meet face to face with many new visitors and reviewers. 

In February, David Hill, a landscape architect and professor from Auburn, met with the team and pushed us to think about how we could use our existing designs and materials to make the park feel like a cohesive project. In March, we met with Andrew Berman, an architect from New York, and Ted Flato, an architect from Texas, who both pushed the team to think about how to make the park a beautiful space using trees and the shape of the walking trail. All of these meetings have helped the team tremendously with the advancement of the design. 

So, what is next? Coming soon, we have our first executive review. This is the first of two formal project reviews that help make sure the project is on track. Between now and then, you can find us working hard but not without the occasional break outside to enjoy the springtime weather.  

See you next time!

– The Smith Park Team 

       


A Neckdown to Rain-member

Student mixing soil

It’s that time of year again…time for Spring “Neckdown” Week! It was a damp week all around Newbern, but the weather didn’t slow us down. All of the students and faculty got their hands dirty helping out.

Around Morrisette House, the Farm got plenty of attention and preparation for the coming growing season. We pulled out cover crops, tarped beds in the field, and started seeds in the greenhouse when the rain caught up to us. The front fence even got a facelift!

Work on the Fabrication Pavilion was one of the biggest Neckdown tasks this semester. A rotating crew of students spent time reinforcing each column to get ready for the pavilion’s second phase. There was almost as much scaffolding as people on site…

Other spots around town got some love too! The model homes and Newbern Town Hall both had facelifts, with lots of cleaning and repainting all around.

Another one of the main (and muddy!) projects for the week happened at Perry Lakes Park. The park boardwalk now has brand-new boards in place, ready for anyone who wants to come visit.

Now that Neckdown is behind us for the semester, it’s time to really dive into the projects. Keep up with each team’s blog posts to see where this spring takes us!

People carrying lumber through woods