#bricksfordays

Six Trees in the Ground, Seven More To Go

Dr.Dprsey and PHF fellows cleanign bricks

On a Saturday morning, the Greensboro Fellows, Dr. Dorsey, and several community members came to the courtyard site to help clean bricks! Together they cleaned about three-quarters of a pallet (roughly 350) worth of bricks. Thank you, Fellows and Dr. Dorsey, it was a great help!

Concrete Pour

Formwork pre-concrete pour

The team finished the formwork, secured the rebar mesh, and taped over the formwork spacers and screws. The slab under the walkway is divided into rectangular pavers, which follow the grid system of the rest of the courtyard, and allow two-inch gaps that correspond with screen and grate placement. This week with the help of contractor, Clyde Fields, the team poured concrete!

Cured concrete before formwork was removed

While waiting for the new trees to be delivered, we began removing the formwork! To make prying the forms out easier, longer pieces of formwork were created at the edges of each rectangular slab piece, with spacers every foot or so.

Crepe Myrtles Arrived!

Thirteen beautiful, single trunk, Natchez Crepe Myrtles arrived on site on a cloudy Thursday morning. The team unloaded all of the trees with the help of 3rd-year students, Mason, and the Bobcat. The trees have grown taller since being tagged at a nursery in northern Alabama! The caliper, or width of the tree trunk, ranges between three and four inches wide. The bottom of the tree canopy is at least six to seven feet tall, allowing people to comfortably wander beneath the canopy.

That Friday morning we, along with 3rd-years and Mason, excavated holes for the first two trees. Considering the size of the site, the trees needed to be planted two at a time before the following holes could be augured. David Hill, AU professor of landscape architecture, arrived to advise and help plant the Crepe Myrtles. The 3rd and 5th-years helped us plant the first six trees! A huge shout out to David for coming from Auburn to assist planting the first half of the new courtyard trees.

More Bricks, Dirt, and Concrete Prep!

The team and assisting students took a trip to Fuller’s Building Supply, in Selma, AL, to re-stack 3,000 bricks! Said bricks had been purchased by the courtyard team a little over a year ago. Due to the pallets sitting outdoors for so long, they started to deteriorate and eventually rotted away. For one day, a crew of five sorted through the broken and whole bricks, and re-stacked them according to brick color on new pallets. Once the bricks were delivered to the site, the cleaning process began! Similarly to the previously found bricks, these have been scrapped of remaining mortar.

Curb formwork removal

Before the site was graded, the students removed the formwork of the concrete curb from the previous week’s pour. They also created a temporary boundary box to retain gravel or dirt from covering the curb and the grinder pump lid.

Grading the site

Batter boards used to indicate edge of gravel underlay
Image of whole site after grading work finished

In order to proceed with construction, the ground needed to be re-leveled. Certain areas of the site needed to come up four or so inches and others needed dirt removed. Tyler, who had previously helped the team with excavation work, returned with his mini-excavator and got the job done in one day. Caleb, Claudia, and 3rd-year students assisted with hand tamping and moving dirt by hand in areas the larger equipment could not reach. About fifty tons or two tandem trucks worth of dirt was utilized to grade the site. And about twenty-five tons of gravel was brought in as an underlay for the brick pad.

Cleaning up the alley

Simultaneously to the site being graded, time was spent on tidying up the building on Beacon Alley. The wooden doors and window trims were painted black to diminish the attention they drew; the black window trim makes the whole window disappear into the shadows rather than sticking out being a bright white.

Prepping for concrete

As formwork under the walkway started, it was necessary to remove a layer of bricks on the door threshold. To ensure that the level of the concrete and interior finished floor have a smooth transition and avoid water coming into the building. Shortly after that, people working on site were split into two groups. One group was to work on the formwork for the porch/stage area and the other to start staking down the formwork along the south and east fa├žade.