#auburnarchitecture

In the trenches

Despite the constant rain and muddy site, the team was able to set the rebar and pour a few days later! By using Steve’s fancy plumb bob, and the previously set batter boards, we were able to find the center of the footings and consequently tie the rebar in the right location. After the rebar was all laid out, pins were staked into the ground (every 5 feet) as a reference where the level of the concrete should be poured to.

Hey, batter batter!

This week, Steve taught us some tips and tricks on setting up batter boards. These batter boards will be used not only as a guide for excavating but also for setting the rebar reinforcement and pouring concrete. The strings that are pulled from stake to stake mark the edges of the footing and the middle string helps to delineate the center, where the screens will connect to the concrete. After the lines were taut and centered, the ground was spray-painted as a reference for digging, and the string was rolled back.

In a day the footing trenches were excavated! Most of it was dug with a mini excavator, but in areas where there were pipes, the digging was done by hand.

Caleb happy we are finally digging the footings!!

Considering the rain in the next couple of days, the team made a provisional cover with 2″x4″ and plywood that was sloped to let the rain shed off to the side. Then tarps were placed on top of the plywood so that the plywood didn’t get soaked.

Check-in next week to see how the rebar was done, and if the weather allows the concrete pour!

Neckdown part 2

The Horseshoe Farm fellows and Dr. Dorsey came out on Sunday and helped prime and scrape the remaining of the block walls. By the end of the day, most of the Beacon Alley wall was primed and a coat of fresh paint put on the other wall!

The team finished installing the new waterlines and aligning the shut-off valve boxes at the north end of the site, as well as adding a connection for a water hose during construction.

This week Luis also came down from Columbiana, Alabama, and volunteered his time with the team. Luis is a certified welder, and one of the people that taught the team how to weld at Jim Turnipseed’s shop. After the galvanization was ground off at the bottom of the bracket connection, Luis welded the plates to the tube in order to make a stiffer connection.

Mason helping deliver the cut grate to the site. Up next grate installation!

Neckdown part 1

As the semester kicked off to a rainy start, the team took advantage of the sunny days during the neckdown week to get things done on-site! With the help of Charlie, Livia, Hannah, and Jackie, the new waterline trench was dug, and the CMU block walls were scraped clean and prepped for painting.

Caleb breaking up the concrete foundation walls
Livia making sure the trench was deep enough…for waterlines

While digging the trench, the team and crew found an assortment of whole bricks, dead metal pipes, old terracotta pipes, glass bottles, and remnants of an old foundation. The found bricks were stacked and will be used either on the masonry building to cover the metal beam or as part of the brick “rug” in the finished ground surface at the south end.

Up next, fascia and soffit to be primed and wall painted!

Then there were eight

After the threaded rods were trimmed, a torque wrench was used to tighten the nuts to HILTI’s requirement, 60 PSI.

Before the team left for the holidays, the walkway structure was all put up! Thanks to Rowe and Jeff’s help the team finished setting up all eight wall plates, and a few days later Devin and Charlie brought some extra muscle and to site. This facilitated lifting and bolting the “arms” and struts into place. The arms, being the assembly of the three horizontal plates welded together, on which the grate will sit. And the strut is the tube that connects the “arms” to the two plate tabs at the bottom of the plate bolted to the wall.

The future main entrance to the walkway, and point where levels were checked throughout the instalation of the brackets.

A 3x4x1/4 inch angle supports the South end of the grate, which is equivalent to only using half of the bracket.