welding

These Welds Were Made for Walkin’!

Hello and welcome back to the Rural Studio Bathhouse blog. Check out what we’ve been up to the past few months!

students pose with thumbs up nect to walkway
Thumbs-up for walkway going up!

At the time of the last update, we were just wrapping up stacking the modules for the outdoor shower’s walls and preparing to install the metal roof structure.

View of project from outdoor shower

We got our good friend Shane back on site to help us out with the installation. First up was the compression frame on the top of the walls. After welding the rods to the frame, we tightened the bolts to the recommended pressure, compressing the wood walls into place.

Next, we lifted the continuous tubes into place. Once they were leveled, we bolted them to the compression frame at the recommended force.

With the tubes in place, we marked the locations for the trusses and lifted them onto the tubes. Shane then welded the three trusses into place. He also welded the diagonal support bracing between the trusses.

Next, we marked out the locations for the purlins, and once again, Shane welded them to the trusses. With the trusses and purlins in place, we welded the tubes to the edges of the trusses and purlins, capping all the open ends. This step makes the trusses and purlins appear as planar surfaces instead of singular objects. With all the welding complete, we cleaned and painted the welds and touched up any other ugly spots on the structure.

Finally, we were ready to put up the sheet metal roof. We started with the north side of the outdoor shower, making sure to measure to set points on the trusses to ensure the spacing of the sheets was even.

We were able to do this very quickly, and it completely transformed the experience of the space. Although it looks like our early renderings, it’s even better than we imagined in reality!

View of Outdoor Shower from outside
Finished roof from outside

On site, we poured the small concrete pad on the top of the boot washing station at the front of the building. Steve helped us with the finishing work and taught us how to do the edging and broom finish. This little slab will support a water hydrant that comes up through it as well as several boot scrubbers and/or a water hose reel.

After we finished installing of the roof structure and completing other site tasks, we made our way back to Columbiana to continue with the rest of the metal fabrication. We began working on the walkway ladders, continuous tubes, plates for the ceilings, and the other miscellaneous roof pieces.

Before we knew it, Pig Roast was almost here! The team made a big push to be able to show off what we could of the metal work on site. We were excited to have the first piece of the walkway done, and Shane came out to the site again to help us put it in place. We also finished a mock-up of the guardrail with the help of Flo and Luis in the shop. The mock-up was clamped in place on site to give visitors an idea of the fully finished walkway. We also set up the outdoor shower so that visitors could climb up and experience the space and views for themselves.

With another year down, it came time to celebrate everyone’s hard work and incredible projects at Pig Roast! Although it was rainy and muggy, nothing could rain on our parade. We had a great time showing off our project and the progress made to all our friends and families. We also enjoyed participating in all the evening festivities as well.

The excitement didn’t last long because we had to get back to work in Columbiana. We started back up on the walkway ladder pieces. This work consisted of us cutting the channels to size, coping the ends of the channels to fit together, drilling any holes, leveling all the pieces, welding the outer frame, adding the bracing tees within the frames, and welding those to the channels. We also cleaned and painted each ladder piece when we finished. We have finished fabricating four of the five walkway ladders.

After we had the four walkway pieces on site, we called on Shane once again to help us out. The installation wasn’t the easiest, but Shane and our two helpers were great, and we lifted all the ladders into place and secured them to the structure.

The day wouldn’t have been complete without a little more excitement, this time with Shane’s truck getting stuck on our muddy site.

View of truck pulling out stuck tow truck
Whoops!

After working so hard on the design of the structure and fabricating the ladder pieces in the shop, it is very rewarding to see the walkway coming together on site. It looks just like our model!

Student balances on walkway structure
Testing our balance and the structure!

While working on the walkway, we also continued making progress on the roof structure. We cut out all the pieces for the trusses with their angles. We then used those pieces to help lay out a jig to build the trusses with, just like how we did with the outdoor shower. This process ensures all the trusses are the same. Then it was time to get to the welding. We laid out the pieces, clamped them to the jig, welded the top side, and then flipped them over to every other side and welded them as we went. Once all 31 trusses were welded, we cleaned up the welds and then painted them. Recently, we were able to transport all of them back to site.

The team is delited with the progress being made in the metal shop, as well as site. We have a few more metal things to fabricate but will be wrapping up the work in Columbiana shortly. We will refocus our efforts on finishing making the modules for the shower pod.

View out of Outdoor Shower at sunset

Thank you so much for reading along, and we already look forward to speaking again soon! Stay tuned for more fun updates.

Students pose above Outdoor Shower roof
Goodbye, Down There!

–  Rural Studio Bathhouse Team

Carla, Ambar, Ashley, and Logan

Respect your Welders!

Hello, and welcome back to the latest edition of the Rural Studio Bathhouse blog. As the semester has progressed, so has the Bathhouse, and we are thrilled to share an update!

Right after the last update, we worked on wood modules for the ceiling of the toilet pod. These modules are built the same way as the wall modules, but they will be stacked horizontally to form the ceiling plane. Now all the modules for the toilet pod are completely finished.

Around the same time, we also finalized the material counts for the rest of the steel pieces of the project and sent those over to Jim Turnipseed. Jim ordered them and got them to his shop in Columbiana, Alabama, for us. Again, we are so thankful to Jim for his abundant generosity and support for our project! Not only has Jim been kind enough to provide materials, but he has also provided us with a large working space inside his shop!

During the week of Spring Break, we packed up and headed to Columbiana for a few days to check everything out.

During the first day in the shop, we looked through our drawings with Flo and Luis, the head fabricators in the shop; getting used to the shop and different machinery; and labeling all of our materials for our later convenience.

The rest of the week we started learning how to weld! We began with welding straight lines on plates and then welding two plates together. After getting the hang of things, we found some square tubing in the shop with dimensions similar to the materials we are using for the roof structure. We then practiced welding these pieces together. With a smaller thickness, these pieces were a little harder to weld together, and we had to speed up the welds a little to avoid burning through this material. We got the feel of it and even practiced filling in large gaps or holes that we burned into the material. Flo and Luis also taught us how to grind to clean up welds and materials.

Once we felt comfortable with welding, we worked on the trusses for the outdoor shower. We made our angled cuts on all the pieces for the three trusses. We created a surface to build the trusses on out of two of our walkway channels, and once we laid out one of the trusses, we used small pieces of angles to create a jig so that the other two trusses would match the first.

By the end of the week, we had completely welded one truss! What a fun Spring Break!

Students pose with finished truss
Look Mom, we did it!

Our goal was to finish the outdoor shower as soon as possible but also to stay on schedule on site. With that in mind, Logan and Ashley worked in the shop, while Carla and Ambar kept going on site with modules. They fabricated the two remaining trusses, the frame for the top of the walls, the continuous tubes which the trusses sit on, and several other pieces.

Next, we cleaned and painted everything, then we loaded up all the pieces and brought them back to site.

Student poses with trailer load of painted metal pieces.
Back to Newbern we go!

Once everything was on site, we unstacked the outdoor shower in the Supershed, labeled each module with its orientation and order, and moved the alignment-bracing interior jig (or Abigail as we call her) into place on the slab with the help of some of our peers.

Following that, we got to stacking! With scaffolding around the slab, we added modules layer by layer. After placing each layer, we checked to make sure the addition was level and that the threaded rods aligned with the holes of the modules. It got a little harder to lift the modules onto the stack as we moved up, but the overall process went smoothly.

We were able to fully stack the outdoor shower in one day!

Now that the walls are in place, the frame and roof structure can be craned into place. We will bolt the frame to the threaded rods, compressing and strengthening the walls. And we will bolt the continuous tubes to the frame and weld the trusses to the tubes.

The team also spent a few more days back in the shop learning how to stick weld, so we could do so on site. Although it was fun to learn a new technique, stick welding was much more difficult for us to pick up, and we’ve decided to leave the on-site welding to professionals for now.

We hope our next steps will all follow shortly, and we are very excited to know that the outdoor shower is nearing completion! Once this roof installation is done, we will take everything we’ve learned from the process back with us to the shop to begin fabricating the rest of the roof structure. We will also begin building the walkway frames and start on the shower pod wall modules.

picture of overall building with finished Outdoor Shower stack

This is such an exciting time in the project, and it is super rewarding to see walls going up and metal coming together. Thank you so much for following along with us and we look forward to providing another exciting update very soon!

–  Rural Studio Bathhouse Team

Carla, Ambar, Ashley, and Logan

Meet Me on the Porch

The Myers’ Home team has been busy preparing the porch structure on the Western face of the home. This porch is unique among previous Rural Studio projects for a few reasons: It’s fabricated from steel, has its own slab, and barely touches the rest of Myers’ Home.

Mildew, Mil-don’t

Looking back, the home was designed for longevity and flexibility through generations. In previous Rural Studio homes with front porches, the space is most often subtractive. This means that the open porch is carved from the main volume of the house and its structural system. In doing so, the rafters are exposed and gaps between trusses are exposed. These must be filled in some way, usually bird blocking. The other solution is a soffit under the eaves.

In both cases, the exposed undersides of the rafters or soffit are nearly always in shade and tend to mildew. Over time the uncovered portion of the truss or rafter can degrade faster than the interiorized segment. In these cases the whole member is still compromised.

The team addresses this problem by eliminating the condition entirely. Myers’ Home has no true eaves, only a slight overhang of the corrugated roofing material. Flashing details are tight and the long Western porch is entirely removed from the structure of the house.

Finding Your Footing

But how’s that little gap mitigated? A separate foundation for the porch is planned. Ideally, this job could be completed with just the team and some extra hands in one morning. This settled into five separate pavers, with two inches of gravel between and roughly a foot of separation from the main house slab.

Before the pavers can be placed though, footings for the metal columns of the porch must be set. This system shook out to be a trench footing, with ten-inch-deep reinforced footings at the columns and a six-inch-deep trench spanning each bay.

Couldn’t do it without a little help from our friends!

With the help of a handful of 5th-year students and professors Andrew Freear and Steve Long, the pour was complete in just about an hour with all levels squared away. The team can look on to the next pour the following week of the pavers.

Prep for the latter involves formwork once again, this time with removable dividers between eight by eight-foot segments. These folks took a leaf out of Horseshoe Courtyard‘s book and used a system of stakes and plywood strips for this maneuver. They then mound backfill dirt around to keep concrete from spilling out beneath the forms. The last step before the concrete arrives is reinforcement with metal mesh and grade pins. The mesh strengthens the concrete as it settles over time and grade pins are fluorescent marked stakes driven to signal the correct level of concrete in the forms.

Finally, the team can tackle their third and last concrete pour of the project. The truck arrived and they were soon in the groove of a process with aid of Patrice’s Home team and Steve. Riley manned the chute; Judith, Daniel, Adam, and Lauren shoveled and screeded; Madeline and Lauren troweled and floated away; and Steve edged each one.

These pavers, being on the porch, are also exposed aggregate which necessitates an additional step after the concrete is finished but still wet. Following a half hour’s wait, Judith misted a specialized concrete retarder atop the fresh pavers, bright ectoplasm green. This allows the majority of the concrete to cure normally while the topmost layer of cement is kept a slurry.

After roughly eight hours, Madeline and Judith return in the evening to hose and scrub the surface of the pavers and wash away the cement. This reveals a texture of the aggregate, in this case pea gravel specially ordered for this type of slab. The team is aiming for a change in surface material between the concrete of the porch and that of the interior as well as a more rugged finish for the home’s entrance.

Weld, Weld, Weld

These three can now focus on the porch structure itself, made entirely of metal with a corrugated roof to match that of the main home. Thanks to the generosity of Studio friend, Jim Turnipseed, the team was able to spend about a week in Columbiana, Alabama at Turnipseed International’s metal shop. There they built jigs, practiced welds, fabricated purlins, and built bents.

With the oversight of teachers Flo and Luis, they quickly learn the equipment, cut pieces to length, and weld up a storm.

Purlins are up first, a good practice run as most welds will be hidden from sight. For east of installation and transport, purlins are designed as mats. These mats are welded in a line and installed as a single unit in each bay. Tables are placed a specified width apart and a simple rectangular jig is made with four ninety-degree angles to catch the mat’s corners.

The bents are pitched with a solid four-inch-wide plate welded atop to catch the purlin mats and provide more tolerance. These take more complex jig-work. The needed angle cannot be achieved in the range of the band saw’s angle. So the extra distance is made up by welding a separate tray to make up the difference.

Following this, the angle for the bents’ top and bottom knee-joint are welded to the tables similarly to the purlin jig. Once the pieces are arranged, baseplates with holes drilled are attached to the bottom of the columns. These baseplates are what will anchor the porch structure to the footings poured earlier.

A big ol’ stack of purlins

The final step in fabrication is to prepare the members for galvanization. A series of half-inch holes must be drilled in all pieces to allow them to drain. This is relevant when components are dipped in the zinc bath stage. Results can be…explosive, otherwise.

Let’s Taco ’bout Halloween

The welded component are shipped off to Mississippi for galvanization! The team is on their merry way back to Newbern to continue site work. But several days earlier the team returned to Hale briefly for the annual Halloween Reviews! Those who may have spent a few days in this neck of the woods may recognize the wall murals from Greensboro’s own Mi Tenampa Mexican restaurant. As leftover students from the previous year, these three spend review day listening in on new thesis and 3rd-year work, attending the costume contest, and eating quite a few Reese’s peanut butter cups.

a red pepper and two human-sized cactus cardboard cutouts stand in front of three people

Bringing Down the Hammer(drill)

While waiting on the return of the porch structure, Madeline, Judith, and Riley move back into finishes and porch groundwork.

Judith and Riley borrow the Studio’s hammer drill and a masonry bit and spend a morning drilling four six-inch-deep holes in each footing. Riley has a specialized jig that expedites the process. After snagging only a bit of rebar, they’re ready for the next stage. Threaded rods are anchored into the holes with epoxy, these will catch those baseplates on the porch columns. With a system of threaded rods and nuts, the team can micro-adjust the levels of the bents upon installation.

That’s what’s going on around town, catch the final stages of finishes soon. Myers’ Home is getting fitted out with cabinetry, sinks, stair treads, and more!

Two Buildings in 10 Hours and 45 Minutes

Live from inside the TMBV Test Buildings, it’s the Thermal Mass and Buoyancy Ventilation Research team! This week the team assembled the structural and insulative envelopes of the Test Building in record time. Instead of traditional timber framing, Structural Insulated Panels (SIP) create the Test Buildings structure. After installing the SIP floors, the students assembled the remaining panels into walls, ceilings, and chimneys. This allowed for each structural plane to be craned into place. Just like a giant Leggo set! The panels were adjusted by two students in an articulating man lift and secured in place using special SIP screws. The joints where walls, floors, and ceiling met were made water and airtight with SIP sealant. In under 11 hours total, all eight walls, two ceilings, and four chimneys came together to create two sturdy, insulated shells. In the coming month, the team will weather-proof the buildings in order to begin installing the thermal mass interiors.

A little bit of Prep!

Building One: 6 Hours

Building Two: 4 hours and 45 minutes

With both buildings assembled, the Thermal Mass and Buoyancy Ventilation Research team is drinking in the rewards of their hard work. This construction method takes a lot of prefabrication and intricate planning to go so smoothly. The team loves the relations of the buildings to each other, to the Cooling Porch, and to the Morrisette Campus. They will be keeping up the momentum so make sure to stay tuned!

The Final Forge

Live from Turnipseed International, it’s the Thermal Mass and Buoyancy Ventilation Research Project! The students with the help of Flo, Luis, and Javier, and the guidance of Jim Turnipseed finished the steel fabrication for the TMBV Test Buildings. In just two weeks, the whole crew built the structural columns and bracing, the stair stringers, the elevated walkway, and all the handrails.

The student team cannot thank Jim Turnipseed enough for his generosity in donating all the material, space, and time to complete the steelwork. Also, lest we forget, the student team would have been lost without the world’s greatest metalworking guides: Flo, Luis, and Javier. The TMBV team will never forget their time at the shop or the remarkable people who made it all happen!

Column Completion

Column weld specifications

With the bracing attachment tabs welded onto the columns, the next step was attaching the top and bottom plates. Most importantly, these plates serve as the connection points from the column to the building and to the ground. After drilling the holes for the anchor bolt and threaded rod connections in the plates, the team built a jig that helped place the columns in the center of the plates.

The team tack welded 8 points on the column to plate connection after centering and clamping them. This secures the plates to column enough so that they can be rotated for the permanent welds. Because the columns hold up the entire buildings, the team triple welded the plates to the columns. They ain’t goin’ nowhere! All 8 columns, 4 per Test Building, were moved out of the shop when complete.

Stairway to Heaven

Overall stair axon with tread support detail

Next up were the stair stringers. Unexpectedly, these babies turned out to be the most complex structure of the bunch. The stringers are composed of 6″ x 3.5″ steel angles. The graduate students had to cut this angle precisely so that the bottom sits flush on the ground and the top meets flat against the 5″ x 5″ steel angle of the elevated walkway. Cap plates, with drilled connection holes, attach to angled cuts so that the stair can be bolted in place.

Each stringer has seven 1.5″ steel angles welded on the inside face, acting as support for the stair treads. The placement of the tread supports needed to be perfectly mirrored between both stringers to avoid a catawampus stair experience. Therefore, the stair tread placement for both stringers was laid out and checked before any welding began. Then welding began!

Tread and handrail placement specification

After welding the treads, it was time for the students to begin the stair handrail. The height of this handrail from the stair stringer is very important as it aligns with the center bar of the walkway handrail. The students rigged yet another jig to ensure the handrails were built as drawn.

The handrails are composed of 1″ tube steel. Therefore, on the open bottoms of the handrails, a cap plate was welded. All welds on the handrails were ground to perfection, enjoy the details below!

And, somehow, the stair handrails did not match up perfectly with the drawings. No big deal though, the graduate students took to their drawings and adjusted the height of the walkway handrail mid bar. Next, the stair handrails needed to be attached to the stringers. This was the most straightforward weld of the stringer, once the placement of the handrails was mirrored on each stringer. The team finished the stringers after a lot of mental math and problem-solving!

Wicked Walkway

Overall walkway axon

Now on to the walkway! The elevated walkway frame which hangs in between the Test Buildings is created out of 5″ x 5″ steel angle. The cut metal grate pieces sit on top of the frame to create the walking surface. The side of the frame will be attached to the buildings with lag screws and therefore needed many holes drilled into it. First, the graduate students cut the angles into four pieces which were to be welded into the walkway frame. Before assembling the frame they drilled the holes for the lag screw connections.

Frame cut pieces and assembly specification

After hole drilling, the team temporarily assembled the frame using lots of clamps. This allowed them to make sure the frame was square before welding. To weld the four pieces together the frame had to be rotated using a crane, all the students, and their teachers. Like the columns, the frame was tacked and then triple welded to fill all gaps and guarantee a strong connection. Below are snapshots of the frame being welded while being held vertically by the crane.

Howdy Handrails

Handrail specifications

Each of the four handrails, which guard the elevated walkway, is slightly different from one another. Of course, they are,… it’s Rural Studio! However, the team created a jig that moved to accommodate the different lengths of handrails but kept the top and center bar locations in place. This way all four handrails were made to the same heights. Having practiced with the stair handrails, the team flew through these welds. The handrails also have end caps to seal the bottom of the square tube.

Before welding, the square tube was cut with 45-degree angles so that the handrails have nice, mitered connections. After welding, the team ground all the welds. Javier and Flo doubled checked all their welds were full and if they weren’t, it was back to welding. With the handrails completed, it was time for a very different task. Moving all the steel onto the trailer.

Load it up!

On the team’s last day at the Turnipseed International, Rowe drove the student truck and 18′ trailer up from Newbern. With lots of help from Flo on the forklift, the steel was loaded into the trailer so it could be driven to the galvanizer. Galvanizing the steel is a process in which a protective zinc coating is applied to prevent rusting. The team and the crew at Turnipseed International parted ways with plans to have a barbeque in celebration of their work sometime soon!

Load it down!

Finally, the steel parts were retrieved from the galvanizer in Birmingham and brought back to rest under the Fabrication Pavilion. The Bobcat was used to remove each column from the trailer as well as the stair stringers and walkway frame.

With all the steel bits and bobbles waiting patiently under the roof of the Pavillion, the team is preparing the raising of the columns. The columns, with bracings, must go up before the SIP panels arrive so they can be attached on top. after the steel walkway and stringer will be nestled between the SIP shells of the Test Buildings. Stay tuned to see how the crazy kids get it all done!